Sl.<br />

Capacity Commissioning Schedule<br />

No. PROJECT DETAILS (MW) Original Actual(A) / As<br />

now Expected<br />

Syn. COD Syn. COD<br />

Comm Comm<br />

II. PROJECTS UNDER CONSTRUCTION<br />

STATE SECTOR<br />

1. Raichur TPP<br />

(M/s KPCL.)<br />

Distt. : Raichur<br />

250<br />

2.<br />

Unit-8 250 07/09 09/09 04/10 (A)<br />

08/09 06/10(A)<br />

Sanctioning <strong>Authority</strong> : State Govt.<br />

Date of Approval by State Govt. : 01.02.2003<br />

06/10<br />

Est. cost : Rs. 92500 Lakh<br />

Latest Cost : Rs. 104 600 Lakh<br />

Exp. during 2003-04 : Rs. 110.05 Lakh<br />

Exp. during 2004-05 : Rs. 5.31 Lakh<br />

Exp .during 2005-06 : Rs. 31.17 Lakh<br />

Exp .during 2006-07 : Rs. 5369.43 Lakh<br />

Exp. During 2007-08 : Rs. 13442.09 Lakh<br />

Exp. During 2008-09 : Rs 54507.47 Lakh<br />

Exp. During 09-10 : Rs. 27449.76 lakhs<br />

Exp. During 10-11 (up to 05/10) : Rs. 62.65 lakhs<br />

Type of fuel :Coal(1.01 MTA from M/s MCL)<br />

Date of Main Plant Order (LOA) : 03.03.07 BHEL (BTG)<br />

Zero Date : 30.03.2007<br />

Bellary TPP St-II<br />

Distt. : Bellary<br />

500<br />

M/s Karnataka Power<br />

Corpn. Ltd<br />

Unit-2 500 11/10<br />

01/11<br />

Date of TEC : NA<br />

02/11 03/11<br />

05/11<br />

Sanctioning <strong>Authority</strong> : State Govt.<br />

Date of Approval by State Govt. : 15.06.2002<br />

Est. cost : Rs.226100 Lakh<br />

Latest Cost : Rs. 226100 Lakh.<br />

Exp .during 2006-07 : Rs.19.87 Lakh<br />

Exp. During 07-08 : Rs. 16773.19 Lakh<br />

Exp. During 08-09 : Rs.37594.43Lakhs<br />

Exp.During 09-10 : Rs. 35229.39 lakhs<br />

Exp.During 10-11 up to 05/10 : Rs. 96.89 lakhs<br />

Financial Closure : -------<br />

Type of fuel : Coal ( CIL/MCL)<br />

Date of Main Plant Order : 31.08.06<br />

Order : BHEL (EPC)<br />

Zero Date : 19.09.2007<br />

06/11<br />

- 94 -<br />

Broad Status<br />

Cooling Tower: Completed.<br />

Chimney: Completed .<br />

CW System: All works completed.<br />

Boiler<br />

-Boiler erection started on 12.12.07. Boiler<br />

drum lifted on 14.08.08.Hydro test<br />

completed on 25.03.09. Light Up<br />

completed on 15.12.09.SBO commenced<br />

on 08.03.10 and completed on 17.03.10.<br />

TG<br />

-Condenser erection started on 05.01.09.<br />

TG erection started on 24.01.09.Box up<br />

completed on 02.12.09.Oil flushing<br />

commenced on 27.01.10 and completed<br />

on 05.03.10. TG put on barring gear on<br />

30.03.10.<br />

- Unit synchronized on oil on 09.04.10 and<br />

coal fired on 22.06.10.<br />

- Unit commissioned i.e. achieved full load on<br />

26.06.10.<br />

CHP: One stream to feed coal to bunkers<br />

commissioned on 22.03.10.<br />

AHP: Work required for synchronization with<br />

coal firing has been completed. Balance works<br />

like pipe laying for disposal wet fly ash, LP<br />

piping in pump house, structural erection of<br />

collector tank in progress.<br />

Reasons for delay:<br />

• Delay in completion of civil works for start of<br />

Condenser & TG erect-ion.<br />

• Late placement of CHP&AHP extension<br />

works.<br />

Availability of Coal<br />

- Boiler erection started on 17.11.08 and in<br />

progress . Drum lifted on 06/04/09. HT<br />

completed on 25 th Jun’10.<br />

- Erection of 4 mills in progress.<br />

- ESP erection started on 19.10.08 and Mills erection<br />

is in progress.<br />

- Foundation work of fans and mills in progress.<br />

-Fabrication & erection of power house, bunker<br />

columns and beams in progress.<br />

- Chimney – Shell concreting completed. Finishing<br />

works are in progress.<br />

- ND Cooling Tower: Shell completed. Erection of<br />

grillage columns in progress.<br />

- Condenser erection commenced on 31.03.10.<br />

- TG erection activities commenced in<br />

Jun’10.<br />

- CW pump house :Staging for pump floor in<br />

progress. Laying and encasement of CW pipe in<br />

progress.<br />

- Clarified water pump house slab concreting is in<br />

progress.<br />

- DM Plant: Roof slab concreting in progress.<br />

- PT Plant: Clarifloculator PCC in progress.<br />

- CHP: Excavation of JT -5&7 in progress. Conveyor<br />

23A/B raft completed, fabrication in progress..<br />

Stacker re-claimer foundation in progress.<br />

- AHP: Ash slurry pump house, Vacuum pump house,<br />

collector tank and silo works are in progress.<br />

- ESP control room & 400 kV Switch yard works in<br />

progress.<br />

- Supply of piping, HPT& LPR by BHEL<br />

Critical<br />

Areas<br />

o Late<br />

receipt<br />

of<br />

boiler<br />

drum<br />

from<br />

BHEL.<br />

o Delay<br />

in<br />

supply<br />

& erection<br />

of<br />

equipm<br />

ent by<br />

BHEL.<br />

o Late<br />

finalizat<br />

ion of<br />

civil &<br />

BOP<br />

package<br />

s by<br />

BHEL<br />

particul<br />

arly<br />

CHP<br />

due to<br />

change<br />

of<br />

scope.