Commissioning Schedule<br />
Sl.<br />
No.<br />
Project Details Capacity<br />
(MW)<br />
Original Actual (A) /As<br />
now expected<br />
Syn. COD Syn. COD<br />
(Com.) (Com.)<br />
B. PROJECT UNDER CONSTRUCTION<br />
STATE SECTOR<br />
1. Kalisindh TPP<br />
RRVUNL<br />
(Distt. Jhalawar)<br />
1200<br />
U –1<br />
600 09/11 01/12 09/11 1/12<br />
(12/11) (12/11)<br />
2.<br />
3<br />
U-2<br />
600 12/11 04/12 12/11 4/12<br />
(3/12) (3/12)<br />
Org. Est. cost Rs. 490006 lakhs<br />
Latest Est. cost Rs. 490006 lakhs<br />
Exp. Upto 3/2009 Rs. 62675 lakhs<br />
Exp.During 2009-10<br />
(upto 8/09)<br />
Rs. 37557 Lakhs<br />
Type of fuel Coal<br />
Fual Linkage Captive- “Parsa East and Kanta<br />
Basin”<br />
Date of main plant Order<br />
Power evacuation system<br />
M/s BGR on 09.07.2008 (EPC)<br />
(Supplier of TG, SG & Aux. – M/s<br />
DEC)<br />
Chhabra TPP Extn.<br />
RRVUNL<br />
(Distt. Baran )<br />
U-3<br />
500<br />
250 09/11<br />
(12/11)<br />
U-4 250 10/11<br />
(3/12)<br />
- 01/12<br />
04//12<br />
- 04/12<br />
07/12<br />
- 45 -<br />
05/12<br />
08/12<br />
Org. Est. cost Rs. 220000 lakhs<br />
Latest Est. cost Rs. 220000 lakhs<br />
Exp. Upto 3/2009 Rs. 21367 lakhs<br />
Exp.During 2009-10 Rs. 90231 Lakhs<br />
Exp.During 2010-11 Rs. 7771 Lakhs<br />
Type of fuel Coal<br />
Fuel linkage Captive- “Parsa East and Kanta<br />
Basin”<br />
Date of main plant Order<br />
Power evacuation system<br />
M/s BHEL on 20.08.2008<br />
Ramgarh CCPP Extn.-<br />
III, RRVUNL<br />
Distt. Jaisalmer<br />
160<br />
GT-1 110 11/11 11/11<br />
ST 50 03/12 03/12<br />
Date of approval by State Cleared State Govt.<br />
Est. approved cost Rs. 64000 Lakhs<br />
Expenditure till Rs. Lakhs<br />
Type of fuel LNG<br />
Fuel Linkage 0.95 mmscmd gas<br />
Date of main plant Order M/s BHEL on 14.07.09 (BTG)<br />
Broad Status<br />
a) LOA Placed on M/s BGR on 09.07.2008 to<br />
execute the project on EPC basis.<br />
b) Zero date of the project is 9 th July’ 08.<br />
c) Coal handling plant is awarded to M/s<br />
TRF.<br />
d) Ash handling plant is awarded to M/s<br />
Macawber Beekay.<br />
e) DM/PT plant awarded to M/s BGRESL.<br />
f) Chimney: 191 out of 275 mtrs. RCC shell<br />
completed.<br />
Unit-1:<br />
a) Boiler erection started on 7 th Dec 09.<br />
b) Boiler drum is lifted on 19 th May’10.<br />
Boiler erection is in progress, 460 MT out<br />
of 5440 MT pressure part erection<br />
completed. 1448/27531 joints completed.<br />
c) ESP erection is in progress.<br />
Unit-2:<br />
a) Boiler erection started on 26th Mar 10.<br />
b) Boiler structure erection is in progress,<br />
2330MT out of a total 5900 MT structure<br />
steel erection completed.<br />
a) LOA Placed on M/s BHEL. An advance of<br />
Rs.7421.25 lacs paid to BHEL.<br />
b) Order for all BOPs except (C&I), has been<br />
placed on M/s Indure.<br />
c) C&I order has been placed on M/s IL Kota.<br />
d) Order for Cooling Tower placed on M/s<br />
Paharpur Cooling Tower.<br />
e) Order for chimney also placed.<br />
f) Order for Switchyard equipment, 6.6kV<br />
switch gear, Generator Transformer,<br />
Station Transformer etc. placed on M/s<br />
ABB.<br />
g) Excavation for boiler foundation<br />
completed. PCC work is in progress.<br />
h) Order for main plant civil works for both<br />
units placed.<br />
a) Main Plant order placed on M/s BHEL on<br />
14.07.2009.<br />
b) Gas supply and transmission agreement<br />
executed with GAIL on 7.8.09 for supply<br />
of 0.95 MMSCMD gas out of which 0.75<br />
MMSCMD will be used for expansion<br />
project and remaining gas will be used for<br />
existing units.<br />
Critical<br />
Areas