BROAD STATUS OF THERMAL POWER PROJECTS IN RAJASTHAN<br />
Project Details<br />
Capacity<br />
(MW)<br />
A. PROJECT COMMISSIONED<br />
1<br />
2.<br />
3.<br />
STATE SECTOR<br />
Dholpur CCPP<br />
RRVUNL<br />
330<br />
Commissioning Schedule<br />
Original Actual (A) /As<br />
now expected<br />
Syn. COD Syn. COD<br />
(Com.) (Com.)<br />
Distt. Dholpur<br />
GT-1<br />
110 02/07 03/07(A)<br />
09/07(A)<br />
09/07(A)<br />
GT-2*<br />
110 03/07 06/07(A)<br />
10/07(A)<br />
10/07(A)<br />
ST*<br />
110 08/07 12/07(A)<br />
03/08(A)<br />
03/08(A)<br />
Date of approval by State Cleared State Govt.<br />
Est. approved cost Rs.115500 Lakhs<br />
Completed cost Rs. 108837 Lakhs<br />
Type of fuel LNG<br />
Fuel Linkage 1.5 mmscmd gas from Panna-<br />
Mukta-Tapti basin by ONGC<br />
Date of main plant Order<br />
* Slipped from 10<br />
M/s BHEL on 5.6.2004 (BTG) at<br />
Rs. 531.30 Crs.<br />
th Plan<br />
Kota TPS St.-V<br />
RRVUNL (Distt: Kota)<br />
195<br />
Unit-7<br />
195 11/08 03/09 05/09(A) 9/09<br />
(2/09) 8/09 (A)<br />
Est. approved cost Rs. 68000 lakhs<br />
Revised cost (Approved in<br />
02/07)<br />
Rs. 88000 lakhs<br />
Cumm. Exp. Upto 3/2009 Rs. 75610 lakhs<br />
Exp.During 2009-10<br />
(upto 9/09)<br />
Rs. 5285 Lakhs<br />
Type of fuel Coal<br />
Fuel Linakage .90 MTPA from SECL<br />
Date of main plant Order BTG contract on BHEL on<br />
30.06.2006 at Rs. 362 Crs.<br />
Suratgarh TPP St-IV<br />
RRVUNL<br />
(Distt. Sriganganagar)<br />
250<br />
U –6<br />
250 09/08 12/08 3/09(A)<br />
(11/08) 8/09(A)<br />
Est. approved cost Rs. 75000 lakhs<br />
Revised cost Rs. 1,00,000 lakhs<br />
Exp. Upto 3/2009 Rs. 95327 lakhs<br />
Exp.During 2009-10 (upto<br />
8/09)<br />
Rs. 4799Lakhs<br />
Type of fuel Coal<br />
- 43 -<br />
09/09<br />
Fuel Linkage 1.16 MTPA from SECL<br />
Date of main plant Order BTG contract on BHEL on 15.06.2006 at<br />
Rs. 402 Crs.<br />
Power Evacuation System Existing system<br />
Broad Status<br />
GT-1: Synchronized on 29 th Mar’07 and<br />
declared on commercial operation on<br />
25.09.07<br />
GT-2: Synchronized on 16 th Jun’07<br />
respectively and declared on commercial<br />
operation on 11.10.07 respectively.<br />
ST: Synchronized on 27.12.2007 and<br />
declared on COD on combined mode on<br />
1st March’08.<br />
a) M/s Desein Pvt. Ltd. Has been appointed<br />
as Consultant.<br />
b) All BOP packages (except C&I) have<br />
been awarded to M/s Tata Project Ltd.<br />
c) Unit synchronized on 30.05.2009.<br />
d) Coal firing done on 4 th Aug’09.<br />
e) Unit commissioned (full load) on 31 st<br />
Aug’09.<br />
a) M/s DCPL have been appointed as<br />
Consultant.<br />
b) All BOP packages (except C&I) have been<br />
awarded to M/s Indure Ltd.<br />
c) DM Plant, PT Plant & FO System: Existing<br />
facility is utilized.<br />
d) Unit Synchronised on 31.3.09.<br />
e) Coal firing done on 21 st Aug’09.<br />
f) Unit commissioned (full load) on 29 th<br />
Aug’09.<br />
Critical<br />
Areas