Jun'2010 - Central Electricity Authority

Jun'2010 - Central Electricity Authority

Jun'2010 - Central Electricity Authority

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Sl.<br />

No.<br />

5<br />

PROJECT DETAILS<br />

Capacity<br />

(MW)<br />

BALCO TPS<br />

Distt. Korba)<br />

M/s Balco<br />

1200<br />

Unit-1 300 07//10<br />

Unit-2 300 02//10<br />

Unit-3 300 03//10<br />

Unit-4 300 09/10<br />

Commissioning Schedule<br />

Original Actual(A) /<br />

As now<br />

Expected<br />

Syn. Comm Syn. Comm<br />

09/10 02/11<br />

04/10 11/10<br />

06/10 09/11<br />

12/10 12/11<br />

Date of TEC : Not Required<br />

Date of Approval by State Govt. :<br />

Est. approved cost : Rs.465000 lakhs<br />

Exp. During 09-10 ( 10/09) :Rs. 180800 lakhs<br />

03/11<br />

12/10<br />

11/11<br />

12/11<br />

Cumm. Exp.<br />

( up to 10/09)<br />

Rs 180800 Lakhs<br />

Financial Closure :<br />

Zero date : 01.11.07<br />

Type of fuel : COAL<br />

Date of Main Plant Order : SEPCO electric Power<br />

Construction Corporation on<br />

Power Evacuation<br />

20.08.07 on EPC basis.<br />

:<br />

- 57 -<br />

Broad Status<br />

a) Implementation agreement signed<br />

b) All statutory clearances received.<br />

c) Coal linkage application is in advance<br />

stage.<br />

d) Water allocation on 18.10.07.<br />

e) The Taraimar ( Durgapur-II) Coal block in<br />

Chhattisgarh allotted.<br />

f) Detailed Engineering 100% completed.<br />

Order finalisation 100% completed.<br />

g) 20/24 shipments dispatched from china and<br />

17 shipments received at site and 2<br />

shipments on transit from port to site.<br />

h) 3 units of boiler drums received at site and<br />

2 units Generator Rotor & Stator received at<br />

site<br />

i) One unit Turbine rotor HIP/IP received at<br />

site and Main transformers for all 4 units<br />

received at site.<br />

j) Chimney for units 1 &2 , 100% civil works<br />

completed, 55% fabrication completed and<br />

18% erection completed.<br />

k) Chimney for unit-3 &4, Civil works -79%<br />

completed and 37% fabrication completed.<br />

l) CHP: Track hopper: 95% civil works &<br />

62% fabrication works completed and Other<br />

works 50% civil & 37% of fabrication 18%<br />

erection works completed. Overall 73%<br />

work completed.<br />

m)AHP: 50% material received at site.<br />

Foundations and Pump house civil works<br />

under progress. Overall 34% work<br />

completed.<br />

n) Cooling tower: For unit-2 80% work<br />

completed. For Unit-3 & 4 work not yet<br />

started. Overall 24% work completed.<br />

o) Main power house Civil works for all 4<br />

units 100% completed and structural work<br />

for 2 units 100% completed.<br />

Unit-2: Drum lifted on 09.05.09. HT<br />

expected in 06/10.<br />

Unit:3 : Drum lifted on 31.05.09. HT<br />

expected in 02/11.<br />

Unit:1 : All major foundations completed.<br />

Drum lifting under progress.<br />

Unit-4: Drum lifting expected in 07/10.<br />

Critical<br />

Areas<br />

The<br />

issue E<br />

Visa to<br />

the<br />

SEPCO/<br />

OEMs<br />

persons<br />

is an<br />

issue<br />

and has<br />

delayed<br />

the<br />

activitie<br />

s like<br />

back<br />

chargin<br />

g, TG<br />

box up<br />

commis<br />

sioning<br />

activitie<br />

s of<br />

critical<br />

equipme<br />

nts.