Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Jun'2010 - Central Electricity Authority
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Sl.<br />
No.<br />
PROJECT DETAILS<br />
BROAD STATUS OF THERMAL POWER PROJECTS IN GUJARAT<br />
Capacity<br />
(MW)<br />
PROJECTS INCLUDED IN 11 TH PLAN<br />
I. PROJECTS COMMISSIONED<br />
STATE SECTOR<br />
1. Dhuvaran CCPP Extn. *<br />
(Distt. Anand)<br />
112.45<br />
2.<br />
GSECL<br />
Commissioning Schedule<br />
Original Actual(A) / As<br />
Syn.<br />
(com.)<br />
now Expected<br />
COD Syn.<br />
(com.)<br />
COD<br />
GT 72 12/05 3/06 (A) -<br />
ST 40 01/06 08/07(A) -<br />
Date of TEC : Not Required<br />
Date of Approval by : 16.10.03 by Govt. of Gujarat<br />
State Govt.<br />
Org. Est.Proj.Cost : Rs.35100 Lakhs<br />
Latest cost of Proj. : Rs. 36800lakhs<br />
Exp. upto 03/07 : Rs.33958 Lakhs<br />
Exp. During 07-08<br />
( Up to 01/08)<br />
: 842 Lakhs<br />
Financial Closure : Achieved<br />
Type of fuel :N.Gas(Supply from M/sGSPL)<br />
Date of Main Plant Order : 24.3.04 on M/s BHEL (EPC)<br />
Zero date of the project<br />
* Slipped from 10<br />
: 25.04.04<br />
TH Plan<br />
Kutch Lignite Extn.<br />
(Distt. Kutch)<br />
GSECL<br />
75<br />
Uni-4* 75 07/06 10/06 10/08(A) 12/09<br />
(09/06) 10/09(A) (A)<br />
Date of TEC : 6.03.03<br />
Date of App. by State<br />
Govt.<br />
: N.A.<br />
Org.Est.Proj.Cost : Rs. 43000 Lakhs.<br />
Latest cost. : Rs. 49000 Lakhs<br />
Exp. Upto 03/07 : Rs. 29186.64 Lakhs<br />
Exp. During 07-08 : Rs. 16216.36Lakhs<br />
Exp.during 08-09 : Rs. 3419.04 Lakhs<br />
Exp.during 09-10<br />
(Upto 12/09)<br />
: Rs. 618.75 Lakhs<br />
Cumulative Expenditure<br />
(Upto 12/09)<br />
: Rs. 49440.79Lakhs<br />
Financial Closure : 29.03.04<br />
Type of fuel : Lignite<br />
Fuel Linkage :GMDCL Lignite Mines<br />
(Panandharo)<br />
Date<br />
Order<br />
of Main Plant : 15.1.04 on M/s BHEL (BTG)<br />
Zero Date of the Project : 29.03.04 (on payment of 15%<br />
advance)<br />
Power Evacuation System: Evacuating in the existing<br />
lines.<br />
* Slipped from 10 TH Plan<br />
- 61 -<br />
Broad Status<br />
OPEN CYCLE<br />
GT - Synchronized on 17.03.06<br />
GT – Taken on full load 30.03.06.<br />
COMBINED CYCLE<br />
Synchronization in combined<br />
cycle<br />
achieved on 13.08.07.<br />
COD achieved on 01.09.07.<br />
Unit Synchronized on oil on 22.10.08<br />
at 04.12 hrs and attained load upto<br />
10MW. Lignite firing achieved on<br />
28.12.08. Full load operation was<br />
expected by 20.01.09 but due to<br />
expn.bellow blast m/c could not be<br />
loaded beyond 35MW. Expn.Bellows<br />
were re-designed. After that, there<br />
was a problem in lignite crusher (not<br />
giving -15mm size). Replacement of<br />
expn. bellows and secondary air fan<br />
shaft completed in 03/09. Lignite<br />
crusher sizing problem again created<br />
problem. M/s BHEL was not allowing<br />
to run the unit until lignite sizing<br />
problem attended fully. Lignite sizing<br />
problem was also resolved. Unit again<br />
synchronized on 20.05.09. As on<br />
22.05.09 unit was running at a load of<br />
45MW. There was problem in<br />
achieving BG due to JOP failure.<br />
Later on the bush of coupling failed.<br />
There was problem in feeder also. Full<br />
load achieved on 01.10.09. COD<br />
achieved on 20.12.09.<br />
Critical<br />
Areas