Sl.<br />

No.<br />

PROJECT DETAILS<br />

BROAD STATUS OF THERMAL POWER PROJECTS IN GUJARAT<br />

Capacity<br />

(MW)<br />

PROJECTS INCLUDED IN 11 TH PLAN<br />

I. PROJECTS COMMISSIONED<br />

STATE SECTOR<br />

1. Dhuvaran CCPP Extn. *<br />

(Distt. Anand)<br />

112.45<br />

2.<br />

GSECL<br />

Commissioning Schedule<br />

Original Actual(A) / As<br />

Syn.<br />

(com.)<br />

now Expected<br />

COD Syn.<br />

(com.)<br />

COD<br />

GT 72 12/05 3/06 (A) -<br />

ST 40 01/06 08/07(A) -<br />

Date of TEC : Not Required<br />

Date of Approval by : 16.10.03 by Govt. of Gujarat<br />

State Govt.<br />

Org. Est.Proj.Cost : Rs.35100 Lakhs<br />

Latest cost of Proj. : Rs. 36800lakhs<br />

Exp. upto 03/07 : Rs.33958 Lakhs<br />

Exp. During 07-08<br />

( Up to 01/08)<br />

: 842 Lakhs<br />

Financial Closure : Achieved<br />

Type of fuel :N.Gas(Supply from M/sGSPL)<br />

Date of Main Plant Order : 24.3.04 on M/s BHEL (EPC)<br />

Zero date of the project<br />

* Slipped from 10<br />

: 25.04.04<br />

TH Plan<br />

Kutch Lignite Extn.<br />

(Distt. Kutch)<br />

GSECL<br />

75<br />

Uni-4* 75 07/06 10/06 10/08(A) 12/09<br />

(09/06) 10/09(A) (A)<br />

Date of TEC : 6.03.03<br />

Date of App. by State<br />

Govt.<br />

: N.A.<br />

Org.Est.Proj.Cost : Rs. 43000 Lakhs.<br />

Latest cost. : Rs. 49000 Lakhs<br />

Exp. Upto 03/07 : Rs. 29186.64 Lakhs<br />

Exp. During 07-08 : Rs. 16216.36Lakhs<br />

Exp.during 08-09 : Rs. 3419.04 Lakhs<br />

Exp.during 09-10<br />

(Upto 12/09)<br />

: Rs. 618.75 Lakhs<br />

Cumulative Expenditure<br />

(Upto 12/09)<br />

: Rs. 49440.79Lakhs<br />

Financial Closure : 29.03.04<br />

Type of fuel : Lignite<br />

Fuel Linkage :GMDCL Lignite Mines<br />

(Panandharo)<br />

Date<br />

Order<br />

of Main Plant : 15.1.04 on M/s BHEL (BTG)<br />

Zero Date of the Project : 29.03.04 (on payment of 15%<br />

advance)<br />

Power Evacuation System: Evacuating in the existing<br />

lines.<br />

* Slipped from 10 TH Plan<br />

- 61 -<br />

Broad Status<br />

OPEN CYCLE<br />

GT - Synchronized on 17.03.06<br />

GT – Taken on full load 30.03.06.<br />

COMBINED CYCLE<br />

Synchronization in combined<br />

cycle<br />

achieved on 13.08.07.<br />

COD achieved on 01.09.07.<br />

Unit Synchronized on oil on 22.10.08<br />

at 04.12 hrs and attained load upto<br />

10MW. Lignite firing achieved on<br />

28.12.08. Full load operation was<br />

expected by 20.01.09 but due to<br />

expn.bellow blast m/c could not be<br />

loaded beyond 35MW. Expn.Bellows<br />

were re-designed. After that, there<br />

was a problem in lignite crusher (not<br />

giving -15mm size). Replacement of<br />

expn. bellows and secondary air fan<br />

shaft completed in 03/09. Lignite<br />

crusher sizing problem again created<br />

problem. M/s BHEL was not allowing<br />

to run the unit until lignite sizing<br />

problem attended fully. Lignite sizing<br />

problem was also resolved. Unit again<br />

synchronized on 20.05.09. As on<br />

22.05.09 unit was running at a load of<br />

45MW. There was problem in<br />

achieving BG due to JOP failure.<br />

Later on the bush of coupling failed.<br />

There was problem in feeder also. Full<br />

load achieved on 01.10.09. COD<br />

achieved on 20.12.09.<br />

Critical<br />

Areas