Sl.<br />

No.<br />

7.<br />

PROJECT<br />

DETAILS<br />

Capacity<br />

(MW)<br />

Commissioning Schedule<br />

Original Actual(A) /<br />

As now<br />

Expected<br />

Syn. Comm Syn. Comm.<br />

Wardha WaroraTPP<br />

(Distt: Chandrapur)<br />

M/s Wardha Power<br />

Company Pvt.Ltd<br />

540<br />

Unit-1 135 02/10 03/10 15.04.10<br />

(A)<br />

- 82 -<br />

06/10<br />

(A)<br />

Unit-2 135 04/10 05/10 06/10 07/10<br />

Unit-3 135 06/10 07/10 08/10 09/10<br />

Unit-4 135 08/10 09/10 10/10 11/10<br />

Org.Est. cost : Rs.241600 lakhs<br />

Exp. upto 03/10 : NA<br />

Exp. During 10-11<br />

( Up to 04/10)<br />

: NA<br />

Financial Closure Achieved on<br />

Type of fuel<br />

24.0108&30.04.09 for Ph-I&II<br />

respectively<br />

:Coal<br />

FSA : In progress<br />

Fuel Linkage : In process<br />

Date of Main Plant Order<br />

(Boiler &TG from Dong Feng,<br />

China)<br />

:EPCContract awarded to<br />

Siachaun Electric Power<br />

Design & Consulting<br />

Co.Ltd.China on 15.05.07.<br />

Power Evacuation System:<br />

220KV transmission line back charged on 05.12.09.<br />

Broad Status<br />

1. All clearances are available.<br />

2. Design & Engineering completed.<br />

3. All the BOPs are in the scope of EPC<br />

contractor and progressing as per<br />

schedule.<br />

Unit-1<br />

Unit oil synchronized on 15.04.10.<br />

Coal firing completed on 05.05.10.<br />

Achieved full load on 05.06.10.<br />

Unit-2<br />

Boiler<br />

1. Boiler drum lifted on 16.03.09.<br />

2. HT completed on 18.08.09.<br />

3. BLU expected in 06/10.<br />

TG<br />

1. TG deck casting completed on 25.04.09.<br />

2. TG erection started on 10.07.09.<br />

3. TG boxed up on 15.02.10.<br />

4. Oil flushing in progress.<br />

Unit-3<br />

Boiler<br />

1. Boiler drum lifted on 07.07.09.<br />

2. HT completed on 15.02.10.<br />

3. BLU expected in 07/10.<br />

TG<br />

1. TG deck casting completed on 26.09.09.<br />

2. Generator stator lifting completed on<br />

15.02.10.<br />

3. TG boxed up on 15.04.10.<br />

4. Oil flushing in progress.<br />

Unit-4<br />

Boiler<br />

1. Boiler drum lifted on 10.01.10.<br />

2. HT completed on 15.03.10.<br />

3. BLU expected in 09/10.<br />

TG<br />

1. TG deck casting completed on 26.11.09.<br />

2. Generator stator lifting completed on<br />

15.03.10.<br />

3. TG box expected in 06/10.<br />

Critical<br />

Areas