Sl.<br />
No.<br />
7.<br />
PROJECT<br />
DETAILS<br />
Capacity<br />
(MW)<br />
Commissioning Schedule<br />
Original Actual(A) /<br />
As now<br />
Expected<br />
Syn. Comm Syn. Comm.<br />
Wardha WaroraTPP<br />
(Distt: Chandrapur)<br />
M/s Wardha Power<br />
Company Pvt.Ltd<br />
540<br />
Unit-1 135 02/10 03/10 15.04.10<br />
(A)<br />
- 82 -<br />
06/10<br />
(A)<br />
Unit-2 135 04/10 05/10 06/10 07/10<br />
Unit-3 135 06/10 07/10 08/10 09/10<br />
Unit-4 135 08/10 09/10 10/10 11/10<br />
Org.Est. cost : Rs.241600 lakhs<br />
Exp. upto 03/10 : NA<br />
Exp. During 10-11<br />
( Up to 04/10)<br />
: NA<br />
Financial Closure Achieved on<br />
Type of fuel<br />
24.0108&30.04.09 for Ph-I&II<br />
respectively<br />
:Coal<br />
FSA : In progress<br />
Fuel Linkage : In process<br />
Date of Main Plant Order<br />
(Boiler &TG from Dong Feng,<br />
China)<br />
:EPCContract awarded to<br />
Siachaun Electric Power<br />
Design & Consulting<br />
Co.Ltd.China on 15.05.07.<br />
Power Evacuation System:<br />
220KV transmission line back charged on 05.12.09.<br />
Broad Status<br />
1. All clearances are available.<br />
2. Design & Engineering completed.<br />
3. All the BOPs are in the scope of EPC<br />
contractor and progressing as per<br />
schedule.<br />
Unit-1<br />
Unit oil synchronized on 15.04.10.<br />
Coal firing completed on 05.05.10.<br />
Achieved full load on 05.06.10.<br />
Unit-2<br />
Boiler<br />
1. Boiler drum lifted on 16.03.09.<br />
2. HT completed on 18.08.09.<br />
3. BLU expected in 06/10.<br />
TG<br />
1. TG deck casting completed on 25.04.09.<br />
2. TG erection started on 10.07.09.<br />
3. TG boxed up on 15.02.10.<br />
4. Oil flushing in progress.<br />
Unit-3<br />
Boiler<br />
1. Boiler drum lifted on 07.07.09.<br />
2. HT completed on 15.02.10.<br />
3. BLU expected in 07/10.<br />
TG<br />
1. TG deck casting completed on 26.09.09.<br />
2. Generator stator lifting completed on<br />
15.02.10.<br />
3. TG boxed up on 15.04.10.<br />
4. Oil flushing in progress.<br />
Unit-4<br />
Boiler<br />
1. Boiler drum lifted on 10.01.10.<br />
2. HT completed on 15.03.10.<br />
3. BLU expected in 09/10.<br />
TG<br />
1. TG deck casting completed on 26.11.09.<br />
2. Generator stator lifting completed on<br />
15.03.10.<br />
3. TG box expected in 06/10.<br />
Critical<br />
Areas