BOC Immingham Dissolved Acetylene Project Environmental Statement: Vol. 2 Main Text<br />

Operation<br />

Operational Phase Conceptual Site Model<br />

7.72 An Operational Phase CSM has been developed to identify any changes to contamination<br />

sources, receptors and pathways and a qualitative contamination risk assessment has been<br />

carried out and compared with the baseline to identify potential impacts during the operational<br />

phase. The methodology has been described earlier in this Chapter. Operation of the proposed<br />

development could include the following potential changes to contamination sources, receptors<br />

and pathways:<br />

� changes to receptors:<br />

- human receptors will now comprise site occupants and visitors.<br />

- controlled waters and offsite receptors will remain the same as for the baseline,<br />

- the development itself will be a new (property) receptor by direct contact with<br />

contaminants in soil and shallow perched water groundwater (if present) and by<br />

accumulation of vapours and ground gas into buildings and enclosed spaces;<br />

� changes to contamination sources (if present) because of construction, which could include<br />

removal or volatilisation of contaminants (source removal);<br />

� importation of ‘clean’ material (if required) which would present pathway barriers to human<br />

and offsite property receptors and reduce infiltration of rainfall and likelihood of leaching of<br />

any contaminants already present from the unsaturated ground to the groundwater;<br />

� changes to pathways which would include placement of large areas of hardstanding acting as<br />

pathway barriers to human and offsite property receptors and reducing contaminant leaching<br />

and run-off to surface water and groundwater receptors, or introduction of any below ground<br />

storage areas which could form new pathways (it is noted that underground storage areas<br />

are not expected for the Dissolved Acetylene Project);<br />

� installation of passive or active ground gas solutions in infrastructure (if necessary) to prevent<br />

accumulation of vapours and ground gas removing pathways to human and property<br />

receptors;<br />

� storage, transport (including above and below ground pipework and manually) and handling<br />

of raw, intermediate, ancillary and waste materials (such as calcium carbide, sulphuric acid,<br />

sodium hydroxide, acetone, glycol, biocide, softeners, paints, thinners, oils, fuels, lime,<br />

chemically treated and wastewater etc.), which could leak spill be entrained in rainwater runoff,<br />

potentially introducing contaminants into the ground or discharge to surface water;<br />

� infiltration of any contaminated firewater to ground during an incident, potentially introducing<br />

contaminants into the ground;<br />

� leaking of contaminants from the Deluge lagoon to ground (following an incident);<br />

� use of plant and equipment on the development site which could accidentally leak fuels and<br />

oils and introduce new contaminants into the ground.<br />

5100935.404 Environmental Statement August 2011 106