BOC Immingham Dissolved Acetylene Project Environmental Statement: Vol. 2 Main Text<br />

Pedestrian and Cyclist Delay and Amenity<br />

12.78 Whilst there will be an increase in the volume of traffic using the designated route, the increase is<br />

not significant (i.e. less than a 30% increase) and is therefore unlikely to have any effect on the<br />

level of delay experienced by pedestrians and cyclists.<br />

Accidents and Safety<br />

12.79 As the traffic speeds of vehicles accessing the site during the operational phase are not expected<br />

to vary from baseline traffic speeds, there is not expected to be any associated increase in<br />

accidents resulting from speeding. The baseline analysis of accident records demonstrated that<br />

there are no significant accident clusters in the vicinity of the site, and therefore there is no reason<br />

to consider that the incidence or seriousness of accidents will be affected.<br />

Driver Delay<br />

12.80 Whilst there will be an increase in the volume of traffic using the designated route, the increase is<br />

not significant (i.e. less than a 30% increase) and is therefore unlikely to have any effect on the<br />

level of delay experienced by other road users.<br />

Significance of Impacts during Construction<br />

12.81 The significance of the construction period on the local highway network has been determined in<br />

accordance with the definitions in Table 12.6. A summary of the results of this process is<br />

presented in Table 12.17.<br />

Table 12.17 Significance of Impacts Operational Peak, Opening Year (2012)<br />

Receptor Sensitivity Magnitude<br />

Hobson Way Low Moderate<br />

Minor<br />

Kiln Lane Low Moderate<br />

Minor<br />

A1173 Low Moderate<br />

Minor<br />

A180 (southbound) Low Moderate<br />

Minor<br />

A180 (northbound) Low Moderate<br />

Minor<br />

High Medium Low Negligible<br />

Minor Not<br />

Significant<br />

Minor Not<br />

Significant<br />

Minor Not<br />

Significant<br />

Minor Not<br />

Significant<br />

Minor Not<br />

Significant<br />

Not<br />

Significant<br />

Not<br />

Significant<br />

Not<br />

Significant<br />

Not<br />

Significant<br />

Not<br />

Significant<br />

12.82 Table 12.17 shows that there is no significant impact during the operational period for all roads<br />

within the study area.<br />

Mitigation Measures<br />

12.82.1 This chapter of the ES has identified that the transport impact of the development on the<br />

surrounding highway network is minimal, and therefore as no significant adverse impacts have<br />

been identified, no mitigation measures are proposed.<br />

12.83 Nonetheless, it is noted that a framework CTMP and FMP have been produced (see Annex 12) in<br />

order to identify and minimise the predicted low volume of construction traffic as well as HGVs<br />

once the site is fully operational.<br />

5100935.404 Environmental Statement August 2011 222