BOC Immingham Dissolved Acetylene Project Environmental Statement: Vol. 2 Main Text<br />

Construction Facilities<br />

3.7 Contractors’ areas (workers facilities, lay-down area, temporary parking facilities etc.) will be<br />

established within the red line boundary area shown on Figure 1.2.<br />

Construction Activities<br />

General<br />

3.8 Construction activities will only take place within the area bounded in red on Figure 1.2. Other<br />

than in the immediate vicinity of the bridge landings, there will be a 7 m maintenance strip along<br />

the top of the bank of Middle Drain and no construction activities will occur within this zone. The<br />

bridge landings will be at least 5 m from the top of the banks and construction activities will not<br />

occur within 5 m of the top of the bank. Other than construction of the emergency access road, no<br />

works will take place within the Anglian Water easement on the south eastern boundary of the<br />

development area. Furthermore, with the exception of the area immediately around the new<br />

bridge access road, construction works are not expected to result in the disturbance to field<br />

margins or scattered scrub.<br />

3.9 At this stage in the Project, a schedule of works and a detailed construction programme are not<br />

available. However, activities associated with the construction phase are likely to be fairly<br />

standard to any construction project for industrial facilities and activities are likely to include:<br />

� site preparation and initial groundworks (for example, formation of temporary site access,<br />

removal of topsoil and excavations);<br />

� piling for buildings and construction of bridge (see following section for further details);<br />

� construction of ground beams, pile caps and solid bases under external areas;<br />

� laying of drainage pipes and creation of drainage infrastructure;<br />

� laying of services from the existing site (across the bridge);<br />

� establishment of site perimeter;<br />

� steel frame erection to all buildings;<br />

� formation of blast walls (Amenity Building only);<br />

� completion of road formations;<br />

� formation of building slabs;<br />

� cladding of buildings;<br />

� mechanical and electrical fit-out;<br />

� installation of process infrastructure steelwork;<br />

� installation of process equipment and ancillaries; and<br />

� testing and commissioning.<br />

Piling<br />

3.10 The ground conditions on the site are not yet known in sufficient detail for the choice of piling<br />

method to have been finalised; however, the current understanding suggests that the possible<br />

options include:<br />

5100935.404 Environmental Statement August 2011 16