BOC Immingham Dissolved Acetylene Project Environmental Statement: Vol. 2 Main Text<br />

18. Summary of Impact Assessment<br />

Introduction<br />

18.1 This Chapter provides a summary of the findings of EIA process for the Dissolved Acetylene<br />

Project. The EIA has been carried out in accordance with the general methodology described in<br />

Chapter 5, and the discipline specific methodologies described in each of the assessment<br />

Chapters (Chapters 6 to 15). In addition, the EIA has taken account of the responses received in<br />

the Scoping Opinion (see Appendix 5A) and other consultation (as described in Chapter 5 and<br />

Chapters 6 to 15). Furthermore, the assessment process has considered the relevant planning<br />

policies at national, regional and local levels (as discussed in Chapter 4 and summarised in<br />

Appendix 4A).<br />

18.2 The definitions of impact significance provided in the following Sections are given in the<br />

assessment Chapters (Chapters 6 to 15). Unless stated otherwise:<br />

� activities and impacts associated with the typical operation of the Dissolved Acetylene Project<br />

are considered to be likely, continuous (whilst the plant is in operation) events with long-term<br />

(permanent within the context of the project lifespan) effects;<br />

� activities and impacts associated with abnormal operation of the Dissolved Acetylene Project<br />

are assumed to be unlikely, infrequent (one-off events) with short-term temporary effects;<br />

� activities and impacts associated with typical construction activities for the Dissolved<br />

Acetylene Project are assumed to be likely, continuous (during typical construction hours)<br />

events with short to medium term (permanent within the context of the construction period<br />

(~9 months)) effects; and<br />

� activities and impacts associated with ground preparation construction activities for the<br />

Dissolved Acetylene Project are assumed to be likely and non-continuous events with<br />

temporary short term effects.<br />

18.3 In reading this Chapter it should be noted that the impact assessment has taken a ‘realistic’<br />

approach in that it has assumed that the Dissolved Acetylene Project will be designed,<br />

constructed and operated in accordance with relevant legislation, regulations, policies and<br />

guidelines and that general ‘good practice’ will be employed. The assessment also takes into<br />

consideration the fact that the Construction Contractor will produce a comprehensive CEMP for<br />

(including a WMP and a CTMP), to be agreed with NELC, and that the operation of the project will<br />

be controlled and managed through incorporation into the existing site’s EMS and through a new<br />

EP. Whereas these environmental management and control measures may be considered as<br />

forms of mitigation, they have been considered to be an integral part of the Dissolved Acetylene<br />

Project proposals and, as such, only specific specialist mitigation measures are provided in the<br />

following Sections. Mitigation measures have not been suggested for impacts with beneficial<br />

effects, or those that are neutral and or negligible.<br />

18.4 The remainder of the Chapter is divided into Sections for each of the environmental discipline<br />

topic areas. A summary of the assessment of cumulative and in-combination effects is also<br />

provided.<br />

5100935.404 Environmental Statement August 2011 298