BOC Immingham Dissolved Acetylene Project Environmental Statement: Vol. 2 Main Text<br />

9.104 There is a risk of flooding from Middle Drain in the event of failure of the pumping station.<br />

However, the station operates with duty and standby pumps and overall the risk is considered to<br />

be minor for the construction and operational phases.<br />

9.105 The site is at moderate to high risk of flooding from groundwater but the main influence on<br />

groundwater levels within the development site will be the tidal levels. The measures incorporated<br />

into the design of the site to manage the tidal and surface water flood risk are suitable for<br />

managing the groundwater flood risk such that the significance of the impact is considered<br />

negligible for both construction and operation.<br />

9.106 There is an increase in compacted soils and or impermeable areas associated with the proposed<br />

development, and, therefore an increase in surface water runoff. As part of the CEMP, surface<br />

water runoff will be managed such that it will not increase the risk of flooding at the proposed<br />

development site, or to land within the surrounding area during construction. During operation, this<br />

will be managed through an appropriately designed surface water drainage system and pumping<br />

station which outfalls into Middle Drain. The site is considered to be at minor risk of flooding from<br />

pluvial surface water during construction and negligible risk of pluvial surface water flooding during<br />

operation.<br />

5100935.404 Environmental Statement August 2011 143