05.02.2013 Views

View - North East Lincolnshire Council

View - North East Lincolnshire Council

View - North East Lincolnshire Council

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

BOC Immingham Dissolved Acetylene Project Environmental Statement: Vol. 2 Main Text<br />

Assessment Step Description<br />

In general, impacts that are assessed to be major or moderate<br />

are considered to result in significant effects; impacts assessed<br />

as negligible are considered to result in insignificant effects; and<br />

minor impacts may result in borderline significant insignificant<br />

effects. This is discussed as relevant in each EIA chapter.<br />

6 Mitigation measures Where, even after the application of ‘good practice’, a significant<br />

adverse effect is identified, specific specialist mitigation measures<br />

to minimise, reduce, offset or avoid such effects are proposed. In<br />

general, mitigation measures are not proposed for beneficial<br />

impacts or those of borderline significance insignificance.<br />

7 Residual impacts Determination of the proposed development’s remaining<br />

significance of effects after mitigation measures are implemented.<br />

Where no mitigation measures are required or proposed the<br />

residual impact is the same as that determined through step 5<br />

above.<br />

8 Recommendations A summary of any recommendations that have been identified<br />

within the assessment process. Recommendations will differ from<br />

mitigation measures in that it will not be assumed that these will<br />

necessarily be adopted and hence they will not be included<br />

accounted for in the assessment of residual impacts.<br />

Recommendations are generally suggestions, or measures that<br />

could be considered further.<br />

9 Summary and<br />

conclusions<br />

A summary of the assessment and key conclusions.<br />

Assessment of Decommissioning Phase<br />

5.8 The acetylene facility is designed to operate for 25 years. If operation after this period is not<br />

feasible, the plant will be required to close and be decommissioned. At this early stage in the<br />

Project, no further information is available relating to the decommissioning phase. However, as a<br />

guideline, it is anticipated that decommissioning activities will be similar to those that could occur<br />

during the construction phase of the Project. At the end of the life of the BOC Dissolved Acetylene<br />

Project, and prior to decommissioning, a detailed assessment will be undertaken to address<br />

environmental impacts associated with decommissioning, thus, and as stated in the Scoping<br />

Report decommissioning has not been discussed in any further detail in this ES.<br />

Assessment of Combined and Cumulative Impacts<br />

5.9 For impacts associated with the Dissolved Acetylene Project that are assessed to be of an<br />

adverse nature, the EIA has considered, so far as is possible, the potential for combined and<br />

cumulative impacts. The assessment of combined and cumulative impacts is an integral part of<br />

the EIA process and ensures that all aspects of potential impacts from the proposed development<br />

have been addressed to ensure minimum overall impact on communities and the natural<br />

environment.<br />

5.10 Combined impacts may occur when an operation (or operations) associated with the Dissolved<br />

Acetylene Project gives rise to several types of impacts on a single receptor (e.g. the combination<br />

of air quality, noise and traffic impacts at a particular residential property).<br />

5100935.404 Environmental Statement August 2011 57

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!