BOC Immingham Dissolved Acetylene Project Environmental Statement: Vol. 2 Main Text<br />

12.22 In line with discussions held with NELC, other committed developments have also been<br />

considered in the assessment.<br />

Data used in the Assessment<br />

Construction Staff Numbers and Shift Patterns<br />

12.23 It is expected that the construction period will see the peak of vehicular activity at the site.<br />

Construction is anticipated to take approximately 9 months commencing in Q1 of 2012.<br />

12.24 Standard construction hours are expected to be from 0800 to 1600 hours Monday to Friday, with a<br />

10% allowance for working from 0800 to 2000 hours Monday to Saturday.<br />

12.25 The construction period will comprise of two phases. The first phase relates to preparation of the<br />

site and construction of site infrastructure. The second phase relates to the process plant fit out,<br />

testing and commissioning. It is likely that Phase 2 will run in parallel with the last two to three<br />

months of Phase 1. For the purpose of this assessment it has been assumed that Phase 1 will run<br />

in parallel to Phase 2 during months 7, 8 and 9 of the construction phase.<br />

12.26 At present it is understood that there will be varying degrees of staffing levels across the nine<br />

month construction period. The Phase 1 construction workforce is expected to peak during the<br />

middle of the construction period, with an average workforce at this time of 22 and a maximum of<br />

26 construction workers being present on the site. The Phase 2 construction workforce will be at<br />

its highest during the last month, with an estimated average workforce of 23 construction workers<br />

on the site. If Phase 1 runs in parallel with Phase 2 there could be a maximum of 38 workers on<br />

site.<br />

Construction Vehicle Movements<br />

12.27 The daily trip generation figures for both the construction and plant fit out phases are provided in<br />

Table 12.1 and Table 12.2.<br />

Table 12.1 Daily Trip Generation Construction: Phase 1<br />

Daily Trips (One-way)<br />

Month Cars Minibus HGVs Total<br />

1 5 0 6 11<br />

2 6 0 7 13<br />

3 5 1 6 12<br />

4 6 2 8 16<br />

5 7 2 11 20<br />

6 6 2 9 17<br />

7 6 1 9 16<br />

8 4 1 7 12<br />

9 3 0 5 8<br />

5100935.404 Environmental Statement August 2011 209