05.02.2013 Views

View - North East Lincolnshire Council

View - North East Lincolnshire Council

View - North East Lincolnshire Council

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

BOC Immingham Dissolved Acetylene Project Environmental Statement: Vol. 2 Main Text<br />

� rotary bored piling (cast in-situ) large or mini rig;<br />

� continuous flight auger (CFA) piling (cast in situ); and<br />

� hydraulic hammer piling (pre-cast) 5 tonne rig.<br />

3.11 Driven (hammer) piling techniques are typically the noisiest. The design team has taken on board<br />

concerns from NE, regarding the potential disturbance to over wintering birds, and CFA or bored<br />

piling techniques will be considered in preference to driven piling. However, there may be<br />

technical reasons relating to the ground conditions which dictate the final selection of the piling<br />

method.<br />

3.12 The buildings and structures that will require piled foundations, and an estimate of the number of<br />

piles, are as follows:<br />

� bridge abutments 24 piles (12 at each end of the bridge);<br />

� Generator Building 22 piles;<br />

� Cylinder and Bundle Filling Building 52 piles;<br />

� Cylinder Examination Shop 24 piles;<br />

� Lime Storage Tanks and Rotary Drum Filters 29 piles;<br />

� Sort Dock 6 piles; and<br />

� Piperack between the Generator Building and the Cylinder Examination Shop -13 piles.<br />

3.13 Piling is likely to take place within the first four months of the construction phase during typical<br />

construction hours (i.e. 0800 to 1600 hours Monday to Friday). The overall duration of the piling<br />

activities will depend on the piling method that is selected. The actual phasing and construction<br />

sequencing will be proposed by the Construction Contractor. It is expected that a single rig would<br />

take two weeks to complete the piling works on the main site. Piling required for the bridge<br />

abutments is likely to be undertaken as a separate phase and is expected to take no more than<br />

one week. A plan showing the anticipated locations of piles is provided in Figure 3.1.<br />

3.14 At this stage in the Project it is anticipated that the depth of the piles will be 14 m to 15 m. This will<br />

be confirmed (or otherwise) as the project develops.<br />

Construction Materials<br />

3.15 It is likely that the majority of materials and process piping will be sourced and fabricated from<br />

within the UK. Where feasible consideration will be given to bringing materials and equipment to<br />

the site through Immingham Dock; however, imports are likely to be limited to a number of specific<br />

vendor package items, e.g. compressor skids.<br />

3.16 Two 2 m high earth embankments will be constructed along three sides of the main process area,<br />

(as illustrated on Figure 3.2). The soil requirements for the these will be met, so far as possible, by<br />

using the material that is excavated as a result of forming the Deluge Lagoon.<br />

5100935.404 Environmental Statement August 2011 17

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!