BOC Immingham Dissolved Acetylene Project Environmental Statement: Vol. 2 Main Text<br />

9 th March 2011: Meeting (NELC, EA, BOC and Atkins) to present the Project to the EA and<br />

to discuss potential flood risk and planning issues.<br />

23 rd March 2011: Issue of Scoping Report 3 to NELC.<br />

8 th April 2011: Meeting (NELC, Natural England (NE), BOC and Atkins) to present the<br />

Project to NE and to discuss potential ecological effects, in particular those<br />

relating to noise from piling activities.<br />

13 th April 2011: Presentation by BOC to Stallingborough Parish <strong>Council</strong> to inform the<br />

council of the Dissolved Acetylene Project proposals.<br />

27 th April 2011: Receipt of Scoping Opinion 4 from NELC.<br />

4-5 th May 2011: Geophysical survey.<br />

23 rd May 2011: Issue of Geophysical Survey Report 5 .<br />

23 rd May 2011: Meeting (NELC, BOC and Atkins) to discuss Planning Policy Statement<br />

(PPS) 25 (Flood Risk) and the Validation Requirements for the Planning<br />

Application.<br />

26 th May 2011: Meeting (<strong>North</strong> <strong>East</strong> Lindsey Drainage Board (NELDB) and Atkins) to gain<br />

an understanding of NELDB’s design requirements for the proposed bridge<br />

over Middle Drain and an understanding of its procedures for granting<br />

approval for works which will affect its watercourses.<br />

26 th May 2011: Submission to NELC of a proposed Schedule of Validation Requirements<br />

for the Planning Application.<br />

6 th June 2011: Confirmation from NELC that a Frame Travel Plan need not be submitted<br />

as part of the Planning Application.<br />

10 th June 2011: Submission of a letter from Atkins to NELC setting out further information in<br />

relation to BOC’s position regarding PPS 25 and the classification of the<br />

development as essential infrastructure (see Appendix 9D).<br />

10 th June 2011: Meeting (EA and BOC) to discuss the EP Application.<br />

16 th June 2011: Submission of a letter from NELC to the EA setting out further information<br />

in relation to BOC’s position regarding PPS 25 and the classification of the<br />

development as essential infrastructure.<br />

21 st June 2011: Submission of report: Information to Inform a Habitats Regulations<br />

Assessment (HRA) Screening 6 .<br />

27 th June 2011: Commencement of ground investigation works.<br />

7 th July 2011: Appointment of Engineering, Procurement and Construction Management<br />

(EPCM) Contractor (Worley Parsons).<br />

13 th July 2011: Submission of the Draft Flood Risk Assessment (FRA) and associated<br />

documents (Annex 9 of the ES) to NELC (to be passed on to the EA).<br />

15 th July 2011: Meeting (Highways Agency (HA) and BOC to discuss the HA comments in<br />

the Scoping Opinion 4 .<br />

8th July 2011: Meeting (Humberside Fire & Rescue Services (HFRS) and BOC) to discuss<br />

emergency preparedness and environmental issues.<br />

4 th August Receipt of a response from the EA in relation to the Draft FRA and<br />

associated documents (Annex 9 of the ES).<br />

Mid-August 2011: Submission of Planning Application.<br />

August 2011 Submission of Report Information to Inform a HRA: Appropriate<br />

Assessment (AA) Stage 2 7 .<br />

August 2011: Issue of Ground Investigation Report (anticipated date).<br />

5100935.404 Environmental Statement August 2011 6