B. Design, construct, erect, support, and remove formwork and related items in accordance with most stringent<br />

requirements of ACI 117 and 347.<br />

C. Form Preparation<br />

1. Clean formwork.<br />

2. Remove rust from steel formwork.<br />

D. Erecting Forms:<br />

1. Solidly butt joints and provide backup at joints as required to prevent faulting at form.<br />

2. Do not tape formwork joints.<br />

3. Just before placing concrete, clean forms and adjacent surfaces again as necessary. Remove wood, sawdust,<br />

chips dirt and other debris.<br />

4. If necessary to grease tie threads, do not allow grease to contact remainder of tie when wall will be exposed<br />

to hydrostatic pressure.<br />

E. Form Release Agent<br />

1. Before placing reinforcing steel, thoroughly coat contact surfaces of forms with form release agent.<br />

2. Apply form release agent evenly without excess drip.<br />

3. Do not allow form release agent to come into contact with concrete surfaces against which fresh concrete<br />

will be placed.<br />

4. Moisten wood forms immediately before placing concrete where form release agents are not used.<br />

F. Provide slab side forms, of form materials specified, full depth, with beveled, level, and smooth top surface for all<br />

slabs where SOV is greater than FF 35 / FL 25.<br />

G. Provide slab side forms such that by placing a 10-foot straightedge, form does not exceed 1/8 inch variation.<br />

H. Prefabricated Access Pit Form: Install in accordance with manufacturer’s instructions.<br />

3.5 VAPOR RETARDER INSTALLATION<br />

A. Install vapor retarder under slabs where shown on drawings.<br />

B. Lap vapor retarder not less than 6 inches with top lap placed in direction of placing concrete.<br />

C. Seal laps continuously with specified tape.<br />

D. Seal punctures and tears in membrane caused by bar chair feet, screed anchors, or utility penetrations with<br />

specified tape.<br />

E. Sequence installation of vapor retarder no more than 40 ft. in advance of laser screed strike-off.<br />

3.6 PLACING REINFORCEMENT<br />

A. Place reinforcing in accordance with most stringent requirements of ACI 117, 301 and 318 and CRSI Manual of<br />

Standard Practice and Placing Reinforcing Bars.<br />

B. Accurately place and secure reinforcement against displacement by firmly wiring at intersections and splices with<br />

not less than <strong>No</strong>. 18 U.S. Standard Gauge annealed wire.<br />

C. Turn wire ends away from concrete exterior.<br />

D. Ensure reinforcing is clean, free from defects and kinks, loose mill or rust scale or coatings that will reduce bond.<br />

03312-16<br />

<strong>Walmart</strong> #<strong>1186</strong> – <strong>Liberty</strong>, <strong>TX</strong> 04/20/11<br />

CMA/10118.034

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!