equired and directed by Wal-Mart Construction Manager and may not be indicated on the Drawings. Install partitions<br />

prior to demolition of existing walls and maintain in dust tight condition until the completion of the new construction.<br />

It is the Contractor's responsibility to prohibit dust and debris from entering the Sales area or any Wal-<br />

Mart-occupied areas and to obtain approval from AHJ for materials/construction configuration and phasing of<br />

temporary enclosures.<br />

1. Dust Drapes:<br />

a. Covering: 6 mil. clear poly sheeting (if allowed by the Authority Having Jurisdiction); otherwise<br />

use Griffolyn type 55 ASFR, anti-static, fire retardant sheeting. Overlap sheeting at joints a<br />

minimum 2’-0" and continuously tape joints. Attach sheeting from ceiling to finish floor for<br />

dustproof condition. If attachment to ceiling is impossible, light framing shall be installed with<br />

sheeting attached all around to prohibit dust penetration.<br />

2. Type A Partitions:<br />

a. Framing: Light gauge metal framing (refer Section 05400) or framing material approved by<br />

Authorities Having Jurisdiction (AHJ). Provide continuous 2x4 top and bottom plates and<br />

continuous bridging and bracing. Continue top plate to bottom side of roof deck.<br />

1) Walls up to 14’-0” may use 3-5/8” - 22 gauge metal studs at 24” o.c. or 2x4’s at 16” o.c.<br />

2) Walls higher than 14’-0” may use 6” - 20 gauge metal studs at 24” o.c. or 2x6’s at 16” o.c.<br />

b. Covering: Install continuous 6 mil clear poly sheets (if allowed by the Authority Having<br />

Jurisdiction); otherwise use Griffolyn type 55 ASFR, anti-static, fire retardant sheeting. Install from<br />

finish floor to roof deck. Tape all joints. Install 1/2" C-D plywood over 6 mil poly. Install 4’x8’<br />

sheets horizontally from finish floor to bottom of roof deck. Insure that blocking is provided behind<br />

each joint. Provide sealant at bottom of plywood at finish floor and continuous sealant against plate<br />

on other side.<br />

3. Type B Partitions:<br />

a. Framing: (same as Type A above).<br />

b. Covering: Install continuous 6 mil clear poly sheets (if allowed by the Authority Having<br />

Jurisdiction); otherwise use Griffolyn type 55 ASFR, anti-static, fire retardant sheeting. Install from<br />

finish floor to roof deck. Tape all joints. Install 1/2" C-D plywood over 6 mil poly. Install 4’x8’<br />

sheets horizontally to bottom of finish ceiling. Extend 6 mil poly to bottom of roof deck. Insure that<br />

blocking is provided behind each joint. Provide sealant at bottom of plywood at finish floor and<br />

continuous sealant against plate on other side.<br />

4. Type D Partitions:<br />

a. Framing: (same as Type A above).<br />

b. Covering: At interior face of partition, install continuous 6 mil clear poly sheets (if allowed by the<br />

Authority Having Jurisdiction); otherwise use Griffolyn type 55 ASFR, anti-static, fire retardant<br />

sheeting. Install from finish floor to roof deck. Tape all joints. Install 1/2" C-D plywood over 6 mil<br />

poly. Install 4’x8’ sheets horizontally to bottom of roof deck. Insure that blocking is provided<br />

behind each joint. At exterior face of partition, install 30 gauge, 24” wide corrugated metal panels<br />

as shown on the Drawings. Fill wall cavities with R-13 batt insulation. Provide sealant at bottom of<br />

plywood at finish floor and continuous sealant against plate on other side.<br />

5. Doors:<br />

a. Single acting doors, opening out, with sturdy closer, closing against gasketed stops on frame to<br />

reduce passage of dust.<br />

6. Sealing:<br />

a. Seal perimeter of partitions and doors to prevent passage of dust. At Type A and B partitions, tape<br />

fastener depressions, joints between panels and joints between panels and floors, ceiling and<br />

columns with 2 in. wide pressure sensitive tape.<br />

7. Mats:<br />

a. Provide mats at doors to reduce tracking of dust. Replace or clean daily.<br />

1.13 FIELD OFFICES AND SHEDS<br />

A. Contractor's Office:<br />

1. Size as required for Contractor's use and to provide space for project meetings.<br />

2. Adequate electrical power, lighting, heating, and cooling to maintain human comfort.<br />

01500-3<br />

<strong>Walmart</strong> #<strong>1186</strong> – <strong>Liberty</strong>, <strong>TX</strong> 04/20/11<br />