E. Secure products in-place with positive anchorage devices designed and sized to withstand stresses, vibration, physical<br />

distortion, or disfigurement.<br />

1.5 PRE-CONSTRUCTION MEETING:<br />

A. Contractor shall schedule a pre-construction meeting in advance of Work defining the construction of the neutralization<br />

wall. Contractor, Air Curtain Manufacturer's Representative (Section 15700), and primary subcontractors<br />

shall attend meeting.<br />

1. <strong>No</strong>tify the Wal-Mart Construction Manager 7 days in advance of scheduled meeting date.<br />

B. Contractor shall be responsible for preparing and distributing a meeting agenda at least two 2 days before the<br />

scheduled meeting. The agenda shall, as a minimum, address the following issues.<br />

1. Discuss the purpose of the neutralization construction as defined herein. Review in detail the scope of<br />

Work relating to construction of wall.<br />

2. Coordination of construction efforts between trades in building the perimeter walls of neutralization area.<br />

3. Responsibilities for sealing penetrations of neutralization wall.<br />

4. Determination of acceptable neutralization wall construction.<br />

5. Review details and specifications regarding Air Curtain construction and equipment and submit<br />

information.<br />

C. Contractor shall record the proceeding of the meeting and prepare minutes reflecting the conversations and discussions.<br />

Copy each attendee in addition to the Wal-Mart Construction Manager.<br />

PART 2 - PRODUCTS<br />

<strong>No</strong>t Used.<br />

PART 3 - EXECUTION<br />

3.1 CONTRACTOR FIELD INSPECTION AND TESTING<br />

A. Inspect Work provided under this Contract to ensure Work is in compliance with Contract requirements.<br />

B. Examination Of Work: Performed prior to beginning Work and prior to beginning each segment of Work and includes:<br />

1. Review of Contract requirements.<br />

2. Review of shop drawings and other submittal data after return and approval.<br />

3. Examination to assure materials and equipment conform to Contract requirements.<br />

4. Examination to assure required preliminary or preparatory Work is complete.<br />

C. Initial Inspection: Performed when representative portion of each segment of Work is completed and includes:<br />

1. Performance of required tests.<br />

2. Quality of workmanship.<br />

3. Review for omissions or dimensional errors.<br />

4. Examination of products used, connections and supports.<br />

5. Approval or rejection of inspected segment of Work.<br />

D. Follow-Up Inspections: Performed daily and more frequently as necessary to assure noncomplying Work has been<br />

corrected.<br />

E. <strong>No</strong> components of the neutralization wall shall be covered or concealed within construction before Work is examined<br />

and found acceptable with respect to neutralization wall construction.<br />

END OF SECTION<br />

01459-2<br />

<strong>Walmart</strong> #<strong>1186</strong> – <strong>Liberty</strong>, <strong>TX</strong> 04/20/11<br />

CMA/10118.034

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!