UniSpec II- <strong>Store</strong> Planning 090105<br />

SECTION 01312 - PROGRESS MEETINGS<br />

PART 1 - GENERAL<br />

1.1 PRE-CONSTRUCTION MEETING<br />

A. A pre-construction meeting will be held at the project site prior to beginning work at a time designated by the<br />

Owner.<br />

B. The Wal-Mart Construction Manager, Contractor’s Project Manager, Contractor’s Superintendent, and major<br />

subcontractors shall be present.<br />

C. The following shall serve as a minimum agenda:<br />

1. Construction schedule.<br />

2. Critical work sequencing.<br />

3. Designation of responsible personnel.<br />

4. Processing of field decisions and changes to the Work.<br />

5. Walk-through inspection and field determination of scope of work and verification of Construction Documents.<br />

1.2 PROGRESS MEETINGS<br />

A. Scheduled progress meetings at the job site are required.<br />

B. The Wal-Mart Construction Manager, Contractor’s Superintendent and major subcontractors (as appropriate to the<br />

agenda) shall be present.<br />

C. The purpose of these progress meetings is to review the schedule of the Project for the next 2 weeks. The<br />

following shall serve as a minimum agenda:<br />

1. Field observations, problems and conflicts.<br />

2. Problems that may impede construction schedule.<br />

3. Review of delivery schedules.<br />

4. Coordination of schedules of different trades and delivery of Owner-furnished products and materials.<br />

Coordination with Wal-Mart Additional Subcontractors and their scope of work.<br />

5. Walk-through inspection and determination of additional scope of work and repairs to the Project.<br />

PART 2 - PRODUCTS<br />

<strong>No</strong>t Used.<br />

PART 3 - EXECUTION<br />

<strong>No</strong>t Used.<br />

END OF SECTION<br />

01312-1<br />

<strong>Walmart</strong> #<strong>1186</strong> – <strong>Liberty</strong>, <strong>TX</strong> 04/20/11<br />

CMA/10118.034

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!