3.6 FINISH REQUIREMENTS:<br />
A. Gloss: Final surface gloss shall be a Specified Overall Gloss Value (SOGV) of not less than 40, and Minimum<br />
Local Gloss Value (MLGV) of 30 as measured using a Horiba IG-320 Gloss Checker.<br />
B. Gloss: Final surface gloss shall be a Specified Overall Gloss Value (SOGV) of not less than 50 and Minimum<br />
Local Gloss Value (MLGV) of 40 as measured using a Horiba IG-320 Gloss Checker.<br />
C. Slip Resistance: Measured static coefficient of friction (SCOF) shall be not less than 0.50 at time of Re-Grand<br />
Opening as measured using an American Slip Meter ASM 825 Digital Meter, Regan Scientific Instruments BOT-<br />
3000 Tribometer, or approved equal.<br />
3.7 FLOOR PROTECTION<br />
A. Protect finished floor from construction traffic and weather until time of Re-Grand Opening.<br />
B. Do not allow water or other liquids to come in contact with finished floor for 72 hours after protective treatment<br />
application.<br />
C. Do not allow acids and acidic detergents to come in contact with slab.<br />
3.8 PRODUCT DISPOSAL<br />
A. Upon completion of densifier and protective treatment, dispose of excess materials as required by local agency<br />
having jurisdiction.<br />
B. Certified applicator shall remove densifier and protective treatment product containers from job site immediately<br />
upon completion of treatment.<br />
3.9 QUALITY ASSURANCE TESTING (BY OWNER)<br />
A. Testing will be performed by Wal-Mart’s Construction Testing Laboratory (CTL) at no expense to the<br />
Contractor. A test report of all measurements and a plan and table of the measurements taken will be prepared by<br />
the CTL for submission.<br />
B. Gloss measurements will be taken once weekly prior to Substantial Completion and at Re-Grand Opening.<br />
Contractor shall notify CTL when floors are ready for testing.<br />
C. Measurement and reporting of SOGV and MLGV by CTL shall be as follows:<br />
1. Collect a minimum of three samples per each bay in random, evenly distributed locations.<br />
2. Record measurement locations on copy of Floor Plan.<br />
3. The average of all samples collected in each bay shall meet or exceed the specified SOGV.<br />
a. If the average of samples collected do not meet the SOGV, collect an addition 3 samples in each<br />
bay for each deficient result unless the individual samples fail to meet the MLGV or the average<br />
of all collected samples in each bay fail to meet the SOGV.<br />
b. If samples fail to meet the SOGV, Contractor shall continue sweeping, scrubbing and polishing<br />
until the SOGV is achieved.<br />
4. <strong>No</strong> single measured value shall be less than MLGV.<br />
a. If one or more samples fall below the MLGV, Contractor shall continue sweeping, scrubbing<br />
and polishing until all samples comply with Specified MLGV and SOGV.<br />
5. Collect and certify final gloss measurements.<br />
D. Slip Resistance Measurements:<br />
03362-6<br />
<strong>Walmart</strong> #<strong>1186</strong> – <strong>Liberty</strong>, <strong>TX</strong> 04/20/11<br />
CMA/10118.034