UniSpec II – <strong>Store</strong> Planning 032709<br />

SECTION 13810 - ENERGY MANAGEMENT SYSTEM (EMS)<br />

PART 1 - GENERAL<br />

1.1 SUMMARY<br />

A. Equipment Furnished by Owner For Installation By Contractor: Owner’s EMS equipment supplier will furnish<br />

EMS equipment as indicated on Drawings and defined in Section 01640 - Owner Furnished Products for installation<br />

by the EMS Installer. The EMS Installer shall be the General Contractor’s installation subcontractor and shall<br />

receive and install Energy Management System equipment scheduled or shown on the Drawings and described in<br />

this Section.<br />

B. Section Includes:<br />

1. Installation of Owner furnished EMS equipment.<br />

2. Making of EMS terminations and installation of cables and conduit as applicable.<br />

3. Proper identification of systems to include labeling Owner furnished EMS equipment.<br />

4. Coordination with Structured Cabling for installation of Ethernet cable.<br />

5. Coordination of Communication with Wal-Mart Support Services for final download of system parameters.<br />

6. Performance of on-site EMS test.<br />

7. Coordination with EMS Supplier for final checkout of Energy Management System.<br />

8. Coordination with Wal-Mart Mechanical Services Department Construction Manager for Start-Up Week<br />

(Supercenters and SAM'S only).<br />

9. Warranty of Energy Management System and Components.<br />

C. Related Sections:<br />

1. Section 06100 - Rough Carpentry: Installation of 3/4-inch plywood backboard as shown on drawings.<br />

2. Section 07840 – Firestopping.<br />

3. Division 16: 120 VAC control wiring.<br />

4. Division 16: Transformers, interface panels, phase loss sensor, and terminate all 120 VAC control wiring<br />

for Energy Management.<br />

5. Division 16: 120 VAC Dedicated circuit for power to system and a 480 VAC 3 phase dedicated circuit for<br />

phase monitor voltage sensing.<br />

D. Contractor Responsibilities:<br />

1. Conduit, bushings, wire ties, fasteners, bolts, panduit labels, hangers, wire connectors, etc.<br />

2. Install all Energy Management equipment scheduled or shown on drawings and described in this Section.<br />

3. Coordinate release of Owner furnished equipment with Wal-Mart Mechanical Services Department.<br />

4. Make all terminations to Owner furnished equipment.<br />

1.2 DEFINITION OF TERMS<br />

A. Work: Complete Installation of equipment and devices in accordance with applicable specifications and as described<br />

in the Drawings, Application Sheets, Manufacturer’s legend sheets and instructions, Request for Bids, and<br />

Purchase Orders.<br />

B. The Owner's authorized representative is defined as the Wal-Mart Mechanical Services Department Construction<br />

Manager.<br />

C. Energy Management contractor shall mean the General Contractor’s, Wal-Mart approved, Subcontractor that is<br />

responsible for performing the Energy Management work as specified on the construction documents. Energy<br />

Management Contractor shall be responsible for compliance with applicable codes, ordinances, and work permits.<br />

13810-1<br />

<strong>Walmart</strong> #<strong>1186</strong> - <strong>Liberty</strong>, <strong>TX</strong> 04/20/11<br />

CMA/10118.034