PROJECT MANUAL Specifications Seafood Removal Walmart Store No 1186 Liberty TX
Specs - Home
Specs - Home
- No tags were found...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
C. As-built Record Documents and Shop Drawings: Record as-builts shall be maintained and submitted for the<br />
primary purpose of recording the locations for concealed interior and exterior underground utilities as specified in<br />
the individual specifications. Legibly record actual measured horizontal and vertical locations of interior and<br />
exterior underground utilities and appurtenances, referenced to permanent surface improvements.<br />
D. Record required as-built information concurrent with construction progress. Do not permanently conceal work<br />
until required information has been recorded.<br />
E. At Project completion, the Contractor shall place the Record Documents (including Building and Civil Record<br />
Drawings, <strong>Specifications</strong>, Addenda, and Change Orders) enclosed in a plastic pipe tube (fixed cap at one end and a<br />
threaded-cap on the other end) for storage in the Electrical Room unless otherwise specified to be located in<br />
another location in the individual Sections. Placement shall be in the presence of and witnessed by the <strong>Store</strong><br />
Manager.<br />
1.8 OPERATION AND MAINTENANCE DATA<br />
A. Operation and Maintenance data shall include a suitably bound set of descriptive literature, maintenance and<br />
operation data, and parts lists for each item of equipment provided under this Contract that will require<br />
maintenance or special operation procedures, including drawings, instructions, or manuals supplied with equipment<br />
furnished by others and installed under this Contract. Submittal of O&M data shall be in the form of placement by<br />
the Contractor of the bound set of O&M data in the Electrical Distribution Center (EDC) within the building. Do<br />
not include O&M data in the Closeout Document Book or submit to Wal-Mart Contract Administration.<br />
Placement of documents shall be witnessed by the <strong>Store</strong> Manager and shall be at least 14 days prior to final<br />
inspection.<br />
1.9 WARRANTIES AND BONDS<br />
A. Prior to Final Application for Payment, submit required warranties and bonds in Closeout Document Book.<br />
1. Assemble documents from Subcontractors, suppliers, and manufacturers.<br />
2. For equipment put into use with Owner's acceptance during construction, submit within ten days after first<br />
operation, listing date of acceptance as start of warranty period.<br />
3. For items of Work delayed materially beyond Date of Substantial Completion, provide updated submittal<br />
within ten days after acceptance, listing date of acceptance as start of warranty period.<br />
END OF SECTION<br />
WAL-MART STORES, INC.<br />
MAINTENANCE DATA SHEET<br />
Complete all Sections Prior To Final Payment<br />
Location:<br />
Size:<br />
<strong>Store</strong>/Club <strong>No</strong>.:<br />
Possession Date:<br />
TYPE OF BUILDING CONSTRUCTION<br />
Walls:<br />
Roof (circle one): SBS BUR EPDM Metal Other (explain)<br />
Roofing Mfg.<br />
Warranty Information. (years)<br />
01770-4<br />
<strong>Walmart</strong> #<strong>1186</strong> – <strong>Liberty</strong>, <strong>TX</strong> 04/20/11<br />
CMA/10118.034