D. As equipment is received, Refrigeration Contractor shall verify Wal-Mart Purchase Order Receipts and forward to<br />

the Contractor for Wal-Mart processing.<br />

E. Contractor shall notify Wal-Mart of equipment received from carrier in damaged condition and shortages.<br />

Damages will be noted on bill of lading. Contractor shall be responsible for failure to note freight damage and<br />

shortages at time of receipt of equipment.<br />

1.17 SPECIFICATIONS FOR REFRIGERATION INSTALLATION<br />

A. Contractor Responsibilities:<br />

1. Coordinate release of Owner and Wal-Mart furnished equipment with Wal-Mart Mechanical Services<br />

Department. The Wal-Mart Mechanical Services Construction Manager is the sole person who can change<br />

delivery dates.<br />

2. Provide crane service to hoist refrigeration equipment directly from truck to mounting position.<br />

3. Provide structural support for refrigeration equipment.<br />

4. Provide opening through outside building wall and provide weather hood.<br />

B. Refrigeration Contractor Responsibilities:<br />

1. Tubing, fittings, insulation for refrigerant lines, unistrut, fasteners, bolts, hangers, etc.<br />

2. Install all refrigeration equipment scheduled or shown on Drawings and described in this Section.<br />

3. Provide labor to unload and set refrigeration equipment scheduled or shown on Drawings and described in<br />

this Section.<br />

4. Make final electrical connections to Owner and Wal-Mart furnished equipment.<br />

5. Provide associated electrical wiring except terminations and slave wires.<br />

6. Install Owner furnished refrigeration controls and sensors.<br />

7. Provide attachment of refrigeration equipment.<br />

1.18 DRAWINGS<br />

A. Provide as built piping drawings, after job completion, in 18- by 24-inch glass frame. Install on compressor room<br />

interior.<br />

1.19 REQUEST FOR INFORMATION SUBMITTAL<br />

A. All Request for Information (RFIs) regarding Refrigeration shall follow the attached copy of the Request for<br />

Information Process Flow Chart.<br />

B. Refer to Specification Section 01255 for RFI Information Submittal Process.<br />

PART 2 PRODUCTS<br />

2.1 OWNER FURNISHED PRODUCTS<br />

A. Refrigerated Cases and Refrigeration Equipment Furnished by Wal-Mart for Installation by Contractor:<br />

Refrigerated cases and refrigeration equipment scheduled or shown on Drawings and described in this Section will<br />

be furnished by Wal-Mart for installation by Refrigeration Contractor.<br />

B. Work Furnished and Installed Under Separate Contracts (NIC):<br />

1. Wal-Mart’s Freezer/Cooler Supplier will perform the following:<br />

a. Delivery and handling of freezer/cooler panels and associated doors and equipment as specified<br />

above.<br />

b. Unloading, uncrating, setting and assembly of walk-in coolers and freezers, and associated doors and<br />

equipment .<br />

15600-5<br />

<strong>Walmart</strong> #<strong>1186</strong> - <strong>Liberty</strong>, <strong>TX</strong> 04/20/11<br />

CMA/10118.034

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!