4. Space joints to allow one continuous placement between bulkheads.<br />

5. Maximum length-to-width ratio for concrete panels defined by walls or joints shall be 1-1/2:1.<br />

6. Do not locate longitudinal construction joints in action alleys.<br />

7. Unless otherwise shown on the Drawings, do not extend reinforcement, corner protection angles, bars or<br />

other fixed metal items through construction joints in slabs on grade or pavements or through joints between<br />

slabs on grade and vertical surfaces.<br />

8. Match joints in walls and curbs with joints in slabs on grade and pavements.<br />

9. Extend joints across tops of walls and curbs unless noted otherwise on Drawings.<br />

10. Isolation Joints: Form isolation joints in accordance with Section 07900.<br />

3.9 CONVEYING<br />

A. Handle concrete from mixer to place of final deposit as rapidly as practicable and in manner which will assure<br />

obtaining specified quality of concrete.<br />

B. Re-tempering: Discard concrete which has already begun to set. Do not re-temper with water.<br />

C. Equipment: Provide mixing and conveying equipment of proper size and design to ensure a continuous flow of<br />

concrete to delivery end. Do not use aluminum pipe or equipment in contact with concrete.<br />

1. Mixers, agitators and non-agitating units: Conform to ASTM C94 and current certification requirements of<br />

Department of Transportation in state where concrete plant is located.<br />

2. Belt Conveyers:<br />

a. Use only types which will not cause segregation.<br />

b. Discharge runs over 30 feet into hopper<br />

3. Chutes: Metal or metal lined not to be installed at slopes greater than 1 vertical to 3 horizontal.<br />

4. Runways:<br />

a. Provide runways or other means above finished concrete level for wheeled conveying equipment.<br />

b. Do not support runways on reinforcing.<br />

c. Do not wheel equipment directly over reinforcing or metal deck.<br />

5. Pumps:<br />

a. Submit to Testing Lab Agency for review, changes to concrete mix to necessitate pumping.<br />

b. Use pump hoses and other slickline components with 5 inch minimum inside diameter.<br />

c. For slickline reducers, reduction in diameter shall not exceed 1 inch over a 5 foot length.<br />

3.10 PLACING CONCRETE<br />

A. Unless otherwise specified, place concrete in accordance with the requirements of ACI 301.<br />

B. The concrete supplier shall have a quality control representative at site for concrete placements.<br />

C. General Contractor and/or the Concrete Floor Subcontractor representative shall be on site during placement of the<br />

concrete.<br />

D. The concrete supplier shall have a quality assurance representative at the site for the entire duration of each<br />

concrete slab placement as a resource to the Contractor.<br />

E. Supervision for the General Contractor and the Concrete Floor Subcontractor shall be on site for the entire<br />

duration of each concrete slab placement.<br />

F. Depositing<br />

1. Do not deposit concrete which has partially hardened or has been contaminated by foreign matter.<br />

2. Deposit concrete continuously in layers of such thickness that no concrete will be deposited on concrete<br />

which has hardened sufficiently to cause seams or planes of weakness.<br />

3. Between construction joints, place concrete in a continuous operation such that concrete is plastic at all<br />

03312-18<br />

<strong>Walmart</strong> #<strong>1186</strong> – <strong>Liberty</strong>, <strong>TX</strong> 04/20/11<br />

CMA/10118.034

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!