Annex XXI Justificació <strong>de</strong> preus<br />

01.04 m³ EXCAVACIÓ DE TERRES PER A BUIDAT DE SOTERRANI<br />

CODI QUANT U RESUM PREU IMPORT<br />

C1312330 0,270 h Pala excavadora giratoria sobre pneumàtics<br />

<strong>de</strong> 9 a 14 t 58,42 15,77<br />

Suma la partida .................... 16,56<br />

Costos indirectes ................. 5,00% 0,83<br />

TOTAL PARTIDA ..................................... 17,39<br />

01.05 m³ EXCAVACIÓ DE RASES I POUS DE FINS A 1,5m DE FONDÀRIA<br />

CODI QUANT U RESUM PREU IMPORT<br />

C1313330 0,106 h Retroexcavadora sobre pneumàtics <strong>de</strong> 8 a 10 t 50,00 5,30<br />

Suma la partida .................... 5,57<br />

Costos indirectes ................. 5,00% 0,28<br />

TOTAL PARTIDA ..................................... 5,85<br />

01.06 m³ EXCAVACIÓ DE RASA PER A PAS D'INSTAL·LACIONS<br />

CODI QUANT U RESUM PREU IMPORT<br />

C1313330 0,160 h Retroexcavadora sobre pneumàtics <strong>de</strong> 8 a 10 t 50,00 8,00<br />

CAPÍTOL 02: FONAMENTS<br />

Suma la partida .................... 8,40<br />

Costos indirectes ................. 5,00% 0,42<br />

TOTAL PARTIDA ..................................... 8,82<br />

02.01 m³ FORMIGÓ DE NETEJA DEL TIPUS HM-20/P/40/I<br />

CODI QUANT U RESUM PREU IMPORT<br />

A0140000 0,250 h Manobre 15,78 3,95<br />

B064500C 1,100 m³ Formigó HM-20/P/40/I 58,87 64,76<br />

A%AUX 2,500 % Despeses auxiliars sobre la mà d'obra 4,00 0,10<br />

Suma la partida .................... 72,25<br />

Costos indirectes ................. 5,00% 3,61<br />

TOTAL PARTIDA ..................................... 75,86<br />