01.05.2014 Views

2. Mangatawa catchment consents for earthworks, storm water ...

2. Mangatawa catchment consents for earthworks, storm water ...

2. Mangatawa catchment consents for earthworks, storm water ...

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

1 Introduction<br />

This report describes the key principles of erosion and sediment control to be employed <strong>for</strong> land<br />

disturbing activities to be undertaken in association with the construction of the Tauranga Eastern<br />

Motorway (TEM). The NZ Transport Agency (NZTA) will engage a Design and Build Contractor to<br />

deliver this project. This Contractor will be responsible <strong>for</strong> preparing the detailed erosion and<br />

sediment control plans (ESCP) based around their construction methodology. The erosion and<br />

sediment control measures are to be designed and implemented in accordance with Environment<br />

Bay of Plenty Guideline No. 2001/03 “Erosion and Sediment Control Guidelines <strong>for</strong> Land Disturbing<br />

Activities, September 2001”.<br />

The resource consent applications lodged with Environment Bay of Plenty (EBOP) in 2008 <strong>for</strong> the<br />

majority of the TEM project (excluding the <strong>Mangatawa</strong> Drain works) contained an example ESCP.<br />

Under those <strong>consents</strong> the Contractor will be required to submit an overall ESCP with EBOP at the<br />

time of construction which will be a contractual requirement between NZTA and the Contractor.<br />

A separate resource consent is now being applied <strong>for</strong> the works associated with the <strong>Mangatawa</strong><br />

Drain. This ESCP provides in<strong>for</strong>mation to demonstrate that appropriate erosion and sediment<br />

control measures can be implemented by providing a plan <strong>for</strong> the <strong>Mangatawa</strong> Drain, the <strong>storm</strong><strong>water</strong><br />

wetland area, a typical culvert installation, and rail bridge embankment stability works. These areas<br />

are representative of much of the project’s construction activities and working area. It is noted that<br />

the application <strong>for</strong> the <strong>earthworks</strong> associated with the main line TEM project was included in the<br />

2008 application.<br />

The ESCPs described in this report are shown on Drawing No.s 3932036-C142, 3932036-CK473,<br />

32932036-CK467A and 3932036-CK461 as included in Appendix A of this document. The ESCPs<br />

detailed in this report give possible erosion and sediment controls that would need to be developed<br />

in more detail by the Contractor <strong>for</strong> the project.<br />

2 Site Description<br />

The TEM alignment runs generally west to east following the coast near Papamoa, changing<br />

direction inland to bypass Te Puke and link with the SH2 intersection near the Te Puke golf course.<br />

The topography is flat to gently undulating. This plan only relates to the drainage works required<br />

between Te Maunga and Domain Road. The <strong>catchment</strong>s relevant to this ESCP include the<br />

<strong>Mangatawa</strong>, Wairakei, Arataki and Maranui <strong>catchment</strong>s. In the current situation, most of the<br />

<strong>catchment</strong>s drain to the Rangataua Bay via the <strong>Mangatawa</strong> drain. The proposed mitigation<br />

measures will provide the same discharge scenario during regular <strong>storm</strong> events. In major <strong>storm</strong><br />

events <strong>water</strong> will spill over the motorway into the Maranui and Wairakei <strong>catchment</strong>s. The Maranui<br />

<strong>catchment</strong> will drain to Rangataua Bay bypassing the treatment pond via a floodway corridor.<br />

This section of the TEM covered by this plan begins near the Baypark Stadium in Papamoa and<br />

follows the East Coast Main Trunk railway line (ECMT) parallel to the Papamoa residential suburb<br />

to the Domain Rd intersection with SH<strong>2.</strong> The total footprint of the site affected by these <strong>earthworks</strong><br />

is approximately 10ha, of which excavation and fill are approximately balanced.<br />

<strong>2.</strong>1 Geology<br />

Geotechnical investigations and subsequent reports undertaken in 2006/07 identify that there are<br />

four geological units found within this length of the TEM alignment. These are summarised below:<br />

Beca // 1 April 2009 // Page 1<br />

3932036 // NZ1-1453076-10 0.10

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!