01.05.2014 Views

2. Mangatawa catchment consents for earthworks, storm water ...

2. Mangatawa catchment consents for earthworks, storm water ...

2. Mangatawa catchment consents for earthworks, storm water ...

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

embankment settlement rates, and the like. The consent process will set out the environmental<br />

bottom lines <strong>for</strong> this project that the Contractor will be required to adhere to. There<strong>for</strong>e the<br />

methodology outlined below is a simplified summary of what may occur.<br />

As part of this application <strong>for</strong> the <strong>Mangatawa</strong> Drain and associated works four situations have been<br />

considered to show that a suitable ESCP can be developed during the detailed design phase to<br />

manage the effects of the works. Due to the varying terrain and contours, the ESCP <strong>for</strong> the<br />

construction of each of these elements should be considered separately, as the works will either<br />

occur at different times or each would have its own discrete mitigation measures. Erosion and<br />

sediment control measures are discussed in Section 4.<strong>2.</strong>1.<br />

3.1.1 <strong>Mangatawa</strong> Drain<br />

The <strong>Mangatawa</strong> Drain flows in a north-westerly direction alongside the south-western boundary of<br />

the TEM from Chainage 1050 to Chainage 6800.<br />

On the eastern side of Kairua Road, enclosed between the rail track and the motorway, a storage<br />

area will be created by excavating approximately 28,000m 3 from the drain. It is likely that some of<br />

this excavated material will be used <strong>for</strong> the 4,000m 3 of fill required to establish a 3 metre wide<br />

1 metre high bund at the top of the drain alignment along the northern side. Excess material will<br />

either be re-used elsewhere on site or appropriately removed off site. Further to this approximately<br />

100 – 200m 3 of excavation works will be undertaken to level the drain bed to a more uni<strong>for</strong>m grade.<br />

3.1.2 Rail Bridge Embankment Stability<br />

Erosion of the Upper <strong>Mangatawa</strong> Drain banks adjacent to and beneath the rail bridge has been<br />

identified as a significant existing issue. Currently the drain alignment flows through two 90 degree<br />

bends when passing beneath the rail bridge. To mitigate the effects and potential <strong>for</strong> erosion along<br />

this section works will include improving the alignment of the drain as well as installing erosion<br />

control measures along both embankments and the drain invert.<br />

Earthworks associated with this work will mainly consist of excavation works required to realign the<br />

drain, however some fill works will be undertaken on the existing bends. The total volume of<br />

<strong>earthworks</strong> <strong>for</strong> this section of the drain is expected to be approximately 14,000m 3 . Gabion baskets,<br />

or similar, will be placed along the drain to protect the banks from erosion with reno mattresses<br />

along the bed of the drain to protect the gabion walls from under scour. Tied back concrete<br />

retaining walls will be constructed under the railway bridge to protect the bridge abutments.<br />

3.1.3 Culvert Extension<br />

a. Flood Bypass from Maranui to <strong>Mangatawa</strong><br />

Approximately 3,000m 3 of excavation is required <strong>for</strong> the installation of two <strong>2.</strong>1 metre diameter<br />

culverts under the TEM and railway track, linking the Maranui and <strong>Mangatawa</strong> Drain. The culverted<br />

bypass will discharge to the <strong>Mangatawa</strong> drain via a weir structure just upstream of the <strong>Mangatawa</strong><br />

Lane Bridge.<br />

b. Sandhurst Culverts<br />

Approximately 2,000m 3 of excavation is required <strong>for</strong> the installation of a 70 metre long, 1.8 metre<br />

diameter culvert beneath the Sandhurst interchange. The culvert will be installed so as to allow<br />

flows from the Maranui swale beneath the interchange.<br />

c. Extension of Maranui Culverts<br />

Beca // 1 April 2009 // Page 3<br />

3932036 // NZ1-1453076-10 0.10

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!