the public road it will be removed by the Contractor using appropriate methods (e.g. sweeper/sucker<br />
truck).<br />
4.<strong>2.</strong>7 Dust suppression<br />
A dust management plan will be developed by the Contractor prior to the start of works and shall<br />
include details of the volume of <strong>water</strong> that is likely to be required, number of <strong>water</strong>ing trucks<br />
required and the location and number of wheel washing facilities. During the dryer summer months<br />
dust control measures will be of high priority to avoid nuisance affects.<br />
In accordance with EBOP guidelines <strong>water</strong> should be applied at a rate of at lest 5mm/day<br />
(50m 3 /hectare) during dry periods. It is highly likely that <strong>water</strong> <strong>for</strong> use as a dust suppressant will be<br />
sourced from a municipal reticulated <strong>water</strong> supply rather than from on-site storage. In this instance<br />
written confirmation will be required from the territorial authority <strong>for</strong> the use of municipal <strong>water</strong>.<br />
4.3 Erosion and Sediment Control implementation Sequence<br />
The anticipated implementation sequence <strong>for</strong> the erosion and sediment controls is as follows:<br />
<strong>Mangatawa</strong> Drain<br />
• Construction of perimeter controls such as clean <strong>water</strong> diversions <strong>for</strong> works;<br />
• Installation of decanting earth bund;<br />
• Installation of Kairua Road controls;<br />
• Drain and storage area <strong>earthworks</strong>;<br />
• Stabilise completed areas as soon as practicable<br />
• Remove decanting earth bund.<br />
Rail Bridge Embankment Stability<br />
• Construction of perimeter controls such as dams and clean <strong>water</strong> diversions <strong>for</strong> works;<br />
• Embankment excavation;<br />
• Gabion basket and Reno Mattress installation;<br />
• Rail Bridge works;<br />
• Fill corners;<br />
• Progressively stabilise completed areas as soon as practicable.<br />
Culvert Extension<br />
• Construction of clean <strong>water</strong> diversions;<br />
• Pipe the existing drains;<br />
• Install clean <strong>water</strong> diversions around outlet construction;<br />
• Progressively stabilise completed areas as soon as practicable.<br />
Lower <strong>Mangatawa</strong> Drain<br />
• Construction of perimeter controls such as silt fences and runoff diversions <strong>for</strong> Stage 1 works;<br />
• Installation of Stage 1 decanting earth bund;<br />
• Stage 1 <strong>earthworks</strong>;<br />
• Stabilise completed Stage 1 areas as soon as practicable;<br />
• Construction of perimeter controls such as silt fences and runoff diversions <strong>for</strong> Stage 2 works;<br />
Beca // 1 April 2009 // Page 10<br />
3932036 // NZ1-1453076-10 0.10