• Make sure bund is stabilised<br />

• Check spillway <strong>for</strong> obstructions<br />

• Ensure no erosion at outlet<br />

Weir Dam • Check that dams are adequately connected in to<br />

embankment with use of sandbags.<br />

• Check <strong>for</strong> accumulated sediment.<br />

• Check discharge points <strong>for</strong> scouring.<br />

Stabilised<br />

Entranceway<br />

Stabilising<br />

Areas<br />

• Install further armouring (sand bags) as required.<br />

• Inspect any structure used to trap sediment from the<br />

stabilised entranceway.<br />

• Check that all stabilised areas have 80% cover.<br />

• Identify areas that require stabilisation.<br />

after rain<br />

Regularly<br />

Regularly and<br />

after rain.<br />

After each<br />

rainfall event.<br />

As works<br />

progress (a<br />

minimum of<br />

once per week).<br />

A further aspect of monitoring should be that associated with weather <strong>for</strong>ecast monitoring. So as to<br />

avoid unstable weather conditions www.metvuw.co.nz should be utilised so critical works can be<br />

planned during a suitable weather window when adverse sediment and erosion effects can be<br />

avoided.<br />

Beca // 1 April 2009 // Page 12<br />