3 • THE BASIC PROCESS PANEL<br />

PROMPTS<br />

Prompt<br />

Name<br />

Type<br />

Capacity<br />

Schedule Name<br />

Schedule Rule<br />

Busy/Hour<br />

Idle/Hour<br />

Per Use<br />

StateSet Name<br />

Description<br />

The name of the resource whose characteristics are being<br />

defined. This name must be unique.<br />

Method for determining the capacity for a resource. Fixed<br />

Capacity will not change during the simulation run. Based on<br />

Schedule signifies that a Schedule module is used to specify the<br />

capacity and duration information for the resource.<br />

Number of resource units of a given name that are available to<br />

the system for processing. Applies only when Type is Fixed<br />

Capacity.<br />

Identifies the name of the schedule to be used by the resource.<br />

The schedule defines the capacity of a resource for a given<br />

period of time. Applies only when type is Schedule.<br />

Dictates when the actual capacity change is to occur when a<br />

decrease in capacity is required for a busy resource unit. Applies<br />

only when Type is Schedule.<br />

Cost per hour of a resource that is processing an entity. The<br />

resource becomes busy when it is originally allocated to an entity<br />

and becomes idle when it is released. During the time when it is<br />

busy, cost will accumulate based on the busy/hour cost. The busy<br />

cost per hour is automatically converted to the appropriate base<br />

time unit specified within the Replication Parameters page of the<br />

Run > Setup menu item.<br />

Cost per hour of a resource that is idle. The resource is idle while<br />

it is not processing an entity. During the time when it is idle, cost<br />

will accumulate based on the idle/hour cost. The idle cost per<br />

hour is automatically converted to the appropriate base time unit<br />

specified within the Replication Parameters page of the Run ><br />

Setup menu item.<br />

Cost of a resource on a usage basis, regardless of the time for<br />

which it is used. Each time the resource is allocated to an entity,<br />

it will incur a per-use cost.<br />

Name of states that the resource may be assigned during the<br />

simulation run.<br />