<strong>Pulacayo</strong> 1 000 t/d Phase I <strong>Feasibility</strong> <strong>Study</strong> - NI 43-101 Technical Report<br />
090644-3-0000-20-IFI-100<br />
11PUD226 740,190.7 7,744,472.6 4,331.8 740,189.3 7,744,472.2 4,318.9 1.5 0.4 12.9<br />
11PUD249 740,647.5 7,744,387.0 4,294.3 740,644.6 7,744,388.6 4,282.8 2.9 -1.6 11.5<br />
11PUD247 740,701.4 7,744,397.1 4,294.8 740,699.6 7,744,396.9 4,283.1 1.8 0.2 11.7<br />
11PUD250 740,794.4 7,744,452.0 4,298.4 740,794.8 7,744,452.8 4,285.6 -0.4 -0.7 12.8<br />
11PUD257 740,901.8 7,744,320.2 4,260.9 740,900.6 7,744,321.7 4,248.1 1.2 -1.5 12.8<br />
11PUD260 740,951.2 7,744,301.3 4,250.1 740,951.8 7,744,302.0 4,239.0 -0.6 -0.7 11.1<br />
11PUD261 740,949.8 7,744,257.9 4,245.5 740,949.1 7,744,262.4 4,234.5 0.8 -4.5 11.0<br />
13 MINERAL PROCESSING AND METALLURGICAL TESTING<br />
To date, four metallurgical programs are complete and a fifth (variability testing) is underway.<br />
Resource Development Inc. (RDi), Denver, USA in 2003, conducted the first program, the<br />
second by UTO (Universidad Técnica de Oruro), Oruro, La Paz, Bolivia in 2009. ED&ED<br />
Ingeniería y Servicios, Lima, Peru completed the third program in 2011 and the fourth<br />
program was conducted by UTO and Maelgwyn Mineral Services (MMSA) Laboratory in<br />
South Africa during the 2012. Maelgwyn Mineral Services (MMSA) is currently conducting the<br />
fifth variability program<br />
In summary, the following test work programs were undertaken and completed:<br />
Program by RDi (2003) on the first sample set (stage 1).<br />
Program by UTO (2011) on the second sample set (stage 2).<br />
Program by ED&ED (2011) on the third sample set (stage 3).<br />
<br />
Program by UTO and Maelgwyn (2012) on the fourth sample set and the fifth<br />
sample set, respectively (stage 4).<br />
Paste thickening test work by FLSmidth on stage 3 tailings samples (2011).<br />
Lead and zinc concentrate assays by SGS (2012).<br />
Concentrate filtration test work by Andritz (2012).<br />
This section of the report summarizes the outcomes and findings of the metallurgical<br />
programs. The test work results used in the Technical-Financial Model<br />
13.1 Resource Development Inc (RDi) Metallurgical Test Program (Stage 1)<br />
In 2002, RDi in USA, received material from the <strong>Pulacayo</strong> <strong>Project</strong> (nine boxes, 120 kg).<br />
Individual drill intervals were combined to generate a single bulk composite sample. This<br />
sample was prepared out of a set of drill core intervals provided (drill holes PuD005 and<br />
PuD006).<br />
RDi undertook preliminary metallurgical test work to evaluate the silver and sulfide base<br />
metals recovery potential utilizing the composite sample from the <strong>Pulacayo</strong> property in<br />
Bolivia. This test work included:<br />