<strong>Pulacayo</strong> 1 000 t/d Phase I <strong>Feasibility</strong> <strong>Study</strong> - NI 43-101 Technical Report<br />

090644-3-0000-20-IFI-100<br />

underground on Levels Zero, 75 and 145 along the access ramp. Each mini sub-station will<br />

consist of LT switchgear (0.4 kV), MT switchgear (3.3 kW) and a transformer (3.3/0.4 MVA<br />

0.5 kV). In case of power failure, the power generator will be used.<br />

16.12.3 Proposed Underground Infrastructure<br />

Underground workshop: The workshop will be located in an old hoist chamber on Level Zero<br />

(see Figure 16.11). It will be used to do daily and minor maintenance on the underground<br />

mining fleet. The services will include a wash bay, fuel and lube bay and a tyre change bay.<br />

Major services will be handled in the existing main workshop on surface. The surface<br />

workshop will be equipped with all the machinery and tools required to perform the tasks.<br />

Collection ponds: Collection ponds will be installed along the access ramp on Level Zero,<br />

Level 75 and Level 147, to collect the water used for drilling and other mining activities. The<br />

ponds will have a length of 30 m, a width of 4m and a height of 2m and they will be able to<br />

store water for 6 hours without the need for pumping (as a contingency). In addition, each<br />

pond will have three centrifugal pumps for dewatering. Two pumps will be used for pumping<br />

the water stored in the pond (one pump will be on standby) and the other pump will be used<br />

to recirculate the fluid and thus prevent any settling of sludge or solids. The pumping system<br />

has been designed in a cascade configuration. The benefits of this configuration include low<br />

energy consumption and reduced pressure in pipelines.<br />

Submersible pumps will also be installed in Candelaria 1 and various other centrifugal<br />

pumps will be installed on surface. The water will be pumped out of the mine via a 150mm<br />

HDPE pipeline to a settler on surface (Level +147). Once the water has been treated, it will<br />

be pumped back to the 300 m 3 storage tank.<br />

Figure 16.11: Location of the Underground Workshop<br />

TWP Sudamérica S.A. Av. Encalada 1257 Of. 801, Santiago de Surco Lima 33, Perú (51-1) 4377473<br />

Page 167