<strong>Pulacayo</strong> 1 000 t/d Phase I <strong>Feasibility</strong> <strong>Study</strong> - NI 43-101 Technical Report<br />

090644-3-0000-20-IFI-100<br />

for 2014; and, Century: 40 to 70 kt/y, closure now set for 2016) and lack of any significant new<br />

projects outside of China. Having said that however, this transition to deficit may prove more<br />

gradual than some anticipate as China continues to invest in both new lead mines (driven also by<br />

relatively attractive zinc and silver prices) and in its currently underdeveloped secondary smelting<br />

industry. Furthermore, environmental issues and concerns can be expected to continue limiting<br />

the ability to expand both primary and secondary supply, with such challenges no longer confined<br />

to developed economies, as China too has experienced considerable environmental scrutiny of<br />

its lead industry over the past few years and, as a result, can be expected to implement stricter<br />

regulation on projects going forward (particularly with respect to secondary smelters).<br />

Elsewhere, the market continues to watch developments at several other western operations, all<br />

of which will have medium term supply side consequences:<br />

<br />

<br />

<br />

<br />

<br />

<br />

At Doe Run’s La Oroya smelter in Peru, which was shuttered in early 2009, discussions<br />

surrounding the recommencement of operations there were initiated with the Humala<br />

government in early 2012 however, several significant issues remain unresolved and a<br />

restart date remains elusive. While it is viewed as likely that these issues will ultimately be<br />

worked out, this is not expected to happen in the near future, keeping important western<br />

smelting capacity and in particular that capable of handling complex, high precious metal<br />

concentrates out of the market.<br />

There are ‘on again/off again’ plans to restart Glencore’s 80,000 t/y lead smelter in Port<br />

Vesme, Italy, which was placed on care and maintenance in 2009. Although expected to<br />

start up earlier this year, this decision has been postponed with the latest rumors focusing<br />

on plans to treat complex, precious metal bearing concentrates there. In conjunction with<br />

this decision however, Glencore is apparently discussing with Xstrata the future for the<br />

latter is 60,000 ton Belledune, New Brunswick lead smelter.<br />

Original plans had Belledune scheduled for closure in tandem with the Brunswick mine<br />

shutdown in 2013. However, the smelter was given an unofficial reprieve in 2011 when it<br />

was unofficially chosen to treat residues from the future Albion process (residue produced<br />

from treatment of Xstrata’s McArthur River bulk concentrates).<br />

More recent plans apparently have Porto Vesme handling the bulk of these residues. Any<br />

deferral of the Porto Vesme restart or an advancement/delay of the Belledune closure will<br />

significantly impact the lead market, but particularly the market for concentrates.<br />

In the United States, Doe Run announced in late June that it will not be proceeding with<br />

the investment in a hydrometallurgical process for treating lead concentrates at its<br />

Herculaneum, Missouri operation but will instead shut that facility at year end 2013 and<br />

sell concentrates into the custom market, thereby removing the last primary lead smelter<br />

in the United States.<br />

On the mine supply side, the low lead content of many of the larger zinc mine projects<br />

(e.g. Bracemac, Perkoa, Lalor Lake, Bisha) and the poor economics of developing leadonly<br />

mines anywhere outside of China, will restrict growth in primary lead output and will<br />

be supportive of lead prices.<br />

TWP Sudamérica S.A. Av. Encalada 1257 Of. 801, Santiago de Surco Lima 33, Perú (51-1) 4377473<br />

Page 216