<strong>Pulacayo</strong> 1 000 t/d Phase I <strong>Feasibility</strong> <strong>Study</strong> - NI 43-101 Technical Report<br />
090644-3-0000-20-IFI-100<br />
Collins, <strong>Apogee</strong> President, and met with <strong>Apogee</strong> Exploration Manager, Mr. Hernán Uribe<br />
Zeballos.<br />
From 24 October to 26 October, TWP Sudamérica conducted a field visit to review the<br />
underground workings, ventilation shafts, underground services and maintenance facilities to<br />
obtain information in support of the underground mine engineering study.<br />
Ryan Illingworth visited the <strong>Pulacayo</strong> site on the 13 th of April 2011.<br />
2.4 Effective Dates<br />
The effective date of this report is 17 January 2012.<br />
There were no modifications on the processing route, engineering design, mine design,<br />
capital and operating costs and financial model between the signature date of this report and<br />
the publication of the Press Release announcing positive <strong>Feasibility</strong> <strong>Study</strong> results dated on<br />
17 January 2013 titled: “<strong>Apogee</strong> <strong>Silver</strong>´s <strong>Pulacayo</strong> <strong>Project</strong> Demonstrates Positive <strong>Feasibility</strong><br />
<strong>Study</strong> Results”.<br />
2.5 Information Sources and References<br />
In addition to site visits undertaken to the <strong>Pulacayo</strong> <strong>Project</strong> in Bolivia, the authors of this<br />
report have relied on information provided by <strong>Apogee</strong>, discussions with John Grewar<br />
(Consulting Metallurgist) and a number of studies completed by other internationally<br />
recognized independent consulting and engineering groups. The authors have made all<br />
reasonable enquiries to establish the completeness and authenticity of the information<br />
provided. TWP has also relied upon other experts. A full listing of the principal sources of<br />
information is included in Section 27 of this report.<br />
2.6 Previous Technical Reports<br />
<strong>Apogee</strong> has previously filed the following technical reports for the <strong>Project</strong> as follows:<br />
<br />
<br />
Technical Report on the Preliminary Assessment of the <strong>Pulacayo</strong> <strong>Project</strong>,<br />
<strong>Pulacayo</strong> Township, Potosi District, Quijarro Province, Bolivia (Pressacco, R.,<br />
Harris, G., Godard, M., Jacobs, C., Micon International Limited, 25 June 2010)<br />
Revised Mineral Resource Estimate, Technical Report for the <strong>Pulacayo</strong> Ag-Pb-Zn<br />
Deposit, <strong>Pulacayo</strong> Township, Potosí District, Quijaro Province, Bolivia (Webster,<br />
P., Cullen, M., Mercator Geological Services Limited, 23 May 2012)<br />
3 RELIANCE ON OTHER EXPERTS<br />
The QPs state that they are qualified persons for those areas as identified in the appropriate<br />
QP “Certificate of Qualified Person” attached to this Report. The authors have relied upon<br />
and disclaim responsibility for information derived from the reports, opinions and statements<br />
of other experts, most of whom are not qualified persons, pertaining to mineral concession<br />
tenure, surface rights agreements, permitting, environmental, social impacts and political<br />
issues. All reasonable endeavors have been made to ensure the accuracy and<br />
TWP Sudamérica S.A. Av. Encalada 1257 Of. 801, Santiago de Surco Lima 33, Perú (51-1) 4377473<br />
Page 16