<strong>Pulacayo</strong> 1 000 t/d Phase I <strong>Feasibility</strong> <strong>Study</strong> - NI 43-101 Technical Report<br />

090644-3-0000-20-IFI-100<br />

<br />

<br />

<br />

Definition and implementation of HSE (Health, Safety and Environment) plan prior to<br />

construction mobilization.<br />

The quality and continuity of the project team through the project phases.<br />

Scope change control.<br />

24.1.3.2 Critical Schedule Activities<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Approval of all required permits.<br />

All stakeholders should be involved and aligned early (integrated team approach).<br />

Identify documentation to be created and updated.<br />

Power line construction<br />

Long lead items should be ordered early (slurry pumps, hydro cyclones, VFDs,<br />

substations, switchgears, switchboards, power transformers, etc.).<br />

Contracting strategy should be selected to avoid tendering delays.<br />

Driving design by constructability and operability requirements, to avoid delays and<br />

modifications.<br />

24.1.3.3 <strong>Project</strong> Schedule<br />

See Figure 24.1.<br />

24.1.3.4 <strong>Project</strong> Milestones<br />

<strong>Project</strong> milestones are summarized in Table 24.2.<br />

Table 24.2: Key <strong>Project</strong> Milestones<br />

Item Start End<br />

Development Phase<br />

Basic Engineering - Mine, Plant & Infrastructure 1 st Quarter, 2013 3 rd Quarter, 2013<br />

Environmental Impact Permitting Process 1 st Quarter, 2013 3 rd Quarter, 2013<br />

EPCM Phase<br />

EPCM Contract Award 2 nd Quarter, 2013 2 rd Quarter, 2013<br />

Detailed Engineering- Mine, Plant & Infrastructure 2 nd Quarter, 2013 4 th Quarter, 2013<br />

Procurement 4 th Quarter, 2013 2 nd Quarter, 2014<br />

Construction Package Process 3 rd Quarter, 2013 4 th Quarter, 2013<br />

Construction (Plant, Mine & Surface Infrastructure) 4 th Quarter, 2013 3 rd Quarter, 2014<br />

Commissioning and Handover 3 rd Quarter, 2014 4 th Quarter, 2014<br />

TWP Sudamérica S.A. Av. Encalada 1257 Of. 801, Santiago de Surco Lima 33, Perú (51-1) 4377473<br />

Page 285