<strong>Pulacayo</strong> 1 000 t/d Phase I <strong>Feasibility</strong> <strong>Study</strong> - NI 43-101 Technical Report<br />

090644-3-0000-20-IFI-100<br />

Oxide NSR Value Calculation Parameters<br />

Ag Price<br />

25 USD/oz<br />

Ag Process Recovery 80%<br />

Ag Smelter Payable 90%<br />

Royalty 13%<br />

Sulphide NSR Value Calculation Parameters<br />

Ag Price<br />

25 USD/oz<br />

Pb<br />

0.89 USD/lb<br />

Zn<br />

1.00 USD/lb<br />

Ag Process Recovery 92%<br />

Pb Process Recovery 79%<br />

Zn Process Recovery 79%<br />

Ag Smelter Payable 100%<br />

Pb Smelter Payable 100%<br />

Zn Smelter Payable 100%<br />

Royalty<br />

Nil<br />

Oxide NSR Open Pit Cut-Off Calculation USD<br />

Process Cost (10,000 tpd) 19.00 USD/ton<br />

General and Administration 2.50 USD/ton<br />

Extra Out of Pit Haulage<br />

1.60 USD/ton<br />

Operating costs per ore ton = (19.00 USD +2.50 USD +1.60 USD) = 23.10 USD/ton<br />

Sulphide SR Open Pit Cut-Off Calculation USD<br />

Process Cost (10,000 tpd) 9.10 USD/ton processed<br />

General & Administration<br />

2.50 USD/ton processed<br />

Extra Out of Pit Haulage<br />

1.60 USD/ton processed<br />

Operating costs per ore ton = (9.10 USD +2.50 USD +1.60 USD) = 13.20 USD/ton<br />

processed<br />

Sulphide NSR Underground Cut-Off Calculation USD<br />

Process Cost (1500 tpd)<br />

12.00 USD/ton processed<br />

General and Administration 2.50 USD/ton processed<br />

Extra out of Mine Haulage 1.00 USD/ton processed<br />

Underground Mining<br />

42.50 USD/ton mined<br />

Operating costs per ore ton = (12.00 USD +2.50 USD +1.00 USD+ 42.50 USD) =<br />

58.00 USD/ton processed<br />

Pit Optimization Parameters<br />

The <strong>Pulacayo</strong> resource model was further investigated with a Whittle pit optimizations to<br />

ensure a reasonable stripping ratio was applied and a reasonable assumption of potential<br />

economic extraction could be made (See Figure 14.19 below). The following parameters<br />

were utilized in the pit optimizations:<br />

TWP Sudamérica S.A. Av. Encalada 1257 Of. 801, Santiago de Surco Lima 33, Perú (51-1) 4377473<br />

Page 135