13.07.2015 Views

Network Statement 2014 - ProRail

Network Statement 2014 - ProRail

Network Statement 2014 - ProRail

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

5. This article is a third-party clause as referred to in Section 6:253 Dutch Civil Code. The railway undertakingaccepts that another railway undertaking that has also accepted these General Terms & Conditions also hasthe right to directly invoke the conditions in these General Terms & Conditions that are relevant to therelationship between the railway undertakings.Article 20.Attributable failureWithout prejudice to the provisions of Title IV above, a party who attributably fails to fulfil its obligations, afterhaving been notified of this failure and given a reasonable period to rectify the situation, but has neverthelessfailed to do so, is liable for the loss incurred by the other party, on the understanding that, except in the case ofintent and/or deliberate recklessness, loss of turnover or profit by the other party is not eligible for compensation.Articles 17, Paragraph 5, and 18, Paragraph 4, of the General Terms & Conditions apply mutatis mutandis.Article 21.Limitation of liability, prescription and force majeure1. The liability of the parties in any form whatsoever is limited to that provided under Title IV, without prejudiceto the right of the parties to demand fulfilment of the provisions of the Access Agreement and/or theseGeneral Terms & Conditions.2. A claim by the railway undertaking or the network manager based on the Access Agreement and/or theseGeneral Terms & Conditions lapses three years from the date of the event that gave rise to the claim.3. In case of the death of persons, a time limit applies of three years starting from the day after decease, but nomore than five years starting from the day after the accident.4. If the claim by the network manager is based on an event with regard to which the railway undertaking hasrecourse against the other party of a transport agreement concluded by the railway undertaking, the claim bythe network manager on the railway undertaking will lapse one month before the expiry of the time limit thatapplies by law or treaty to the claim by the railway undertaking on the other party of a transport contractconcluded by the railway undertaking.5. If the claim by the railway undertaking is based on an event governed by a transport agreement concluded bythe railway undertaking whereby the railway undertaking takes recourse against the network manager, theclaim by the railway undertaking on the network manager will lapse one month after expiry of the time limitthat applies by law or treaty to the claim governed by the transport agreement.6. Prescription is suspended if one of the parties submits the dispute to a body in the sense of Article 28 or if thematter is submitted to an arbitration board.7. The network manager and/or the railway undertaking are in case of force majeure not liable for any losswhatsoever. Force majeure in the sense of these General Terms & Conditions also includes the meaninggiven thereto by law and legal precedents. Also regarded as force mature are power failures not caused bythe network manager, suicides or attempts thereto, behaviour by animals, national or local strikes or workstoppages, whether or not organised, at the company of the network manager and/or of the railwayundertaking.8. The provisions of Paragraph 7 are without prejudice to the obligations of the network manager under Section7, Paragraph 2, Railways Act.9. In case auxiliary staff incur losses which can be attributed to both the network manager and the railwayundertaking, the network manager and the railway undertaking now for then indemnify one another againstany claims by axillary staff for compensation insofar as such is attributable to the network manager and therailway undertaking, respectively. This indemnification also applies to claims for compensation that isattributable entirely to the network manager and for which the auxiliary staff brings a claim against the railwayundertaking, and vice versa.10. in case a scheme applies between the network manager and the railway undertaking for the compensaton ofa specific loss event, the network manager and the railway undertaking now for then indemnify one anotheragainst any claims by auxiliary staff engaged by the network manager and the railway undertaking,respectively, relating to the loss event in question.Title V.Financial stipulationsArticle 22.User and reservation charges1. The user charges are calculated subject to the relevant provisions of the <strong>Network</strong> <strong>Statement</strong>.2. The railway undertaking and the network manager agree on a user charge of nil for the use of the railwayinfrastructure for the performance of instructions by the network manager with regard to the management ofthe railways.3. Trains for which no user charge is due under the terms of this provision will receive no timetable draftingsupport by the One-Stop-Shop of the network manager.4. In order to determine the user charge for the service as referred to in Article 2a of Annex 2 of Directive2001/14/EC, the railway undertaking will provide the network manager with invoices, including theaccompanying proof of payment, for the traction power purchased by the railway undertaking. The railwayappendix 5 Model Access Agreement and General Terms & Conditions<strong>Network</strong> <strong>Statement</strong> <strong>2014</strong> Combined <strong>Network</strong> - version 1.0 dated 9 January 2013 page 110

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!