(b) During and After Retreading. As set forth in paragraph 4.1 <strong>of</strong><br />

ZZ-T-441H, the Government reserves the right to perform any <strong>of</strong> the inspections as<br />

provided in the specification for compliance with prescribed contract requirements. A<br />

representative <strong>of</strong> the user activity should establish the inspection procedure with the<br />

Contracting Officer in order that quality checks <strong>of</strong> the contractor’s plant can be<br />

arranged. A visit to the retreading plant to observe craftsmanship, process controls,<br />

condition <strong>of</strong> processing equipment, quality <strong>of</strong> the rubber used, and cleanliness <strong>of</strong> the<br />

shop provides the necessary confidence level for quality assurance. When the<br />

retreaded tires are returned to the user, the activity's representative who has become<br />

familiar with the contractor's retreading process should inspect each tire. Retreaded<br />

tires found to be defective should be returned to the contractor (at the contractor's<br />

expense) for corrective action. Activity inspections shall verify that the newly delivered<br />

retreaded tire is on the original Navy casing. Also, additional visual inspections are to<br />

be performed as outlined in Tables II and III <strong>of</strong> Specification ZZ-T-441H, to determine<br />

any defective material used, poor processing, or poor workmanship.<br />

c. Tire Marking/Identification. Tire labeling <strong>of</strong> ownership shall be established<br />

by user activities in the following areas:<br />

(1) On tire casings furnished to a contractor for retreading/repair service.<br />

(2) On popular size tires under specific conditions.<br />

(a) To improve local control and accountability.<br />

(b) As a deterrent to pilferage.<br />

Tire labeling/marking shall be by either patch or branding for permanent identification<br />

and shall be made up <strong>of</strong> enough lettering to spell out "USN activity". This label is to be<br />

located on or into the area <strong>of</strong> the tire side wall (but not in the scuff ribs) and shall not<br />

interfere with other DoT required markings. Branded letters shall be approximately<br />

1/16 to 1/8 inches deep, measured from the surface immediately surrounding the<br />

lettering.<br />

4-1.11 Preventive Maintenance Procedures For Construction And Allied<br />

<strong>Equipment</strong> (Less Weight Handling <strong>Equipment</strong>)<br />

4-1.11.1 General. Preventive maintenance (PM) principles and general procedures set<br />

forth in paragraphs 4-1.9 through 4-1.13 are equally applicable to all construction<br />

equipment. (See the <strong>NAVFAC</strong> P-307 for weight handling equipment.) Maintenance<br />

inspections and services shall be performed as prescribed by the manufacturer in the<br />

maintenance manual provided with the equipment and at the recommended<br />

frequencies. The frequencies shall generally be based on hours <strong>of</strong> operation as<br />

recorded on an hour meter, rather than fixed time intervals, except for the daily services<br />

performed by the operator.<br />

4-1-39