Old Parliament House and Curtilage Heritage Management Plan <strong>2008–2013</strong><br />

XI<br />

Figure 1: Process to develop this plan<br />

1. Plan developed pursuant to 324S and 341S EPBC Act 1999<br />

2. Plan project supported by joint departmental Working Group & Expert Advisory Panel<br />

OPH & NCA prepare plan<br />

for the Minister for the<br />

Environment,<br />

Heritage and the Arts<br />

3. Define scope of plan<br />

4. Identify heritage values (Commonwealth & National)<br />

5. Articulate attributes of the heritage values<br />

All drafts and processes were developed and reviewed by the Old Parliament House Working Group and the Expert Advisory Panel<br />

6. Revise statement of significance<br />

7. Risk & opportunity analysis related to protection of heritage values<br />

8. Map heritage values of the place<br />

9. Map sensitivity to change of heritage values<br />

10. Define key management objectives & outcomes<br />

11. Analyse & amalgamate mapped heritage values to a set of management zones<br />

12. Develop action assessment process<br />

13. Define policies & actions to address identified issues<br />

14. Preliminary draft Heritage Management Plan<br />

15. Review preliminary draft by Working Group & Expert Advisory Panel<br />

16. Exposure Draft Heritage Management Plan<br />

17. Invite comments from targeted stakeholder group and review by Working Group, Expert<br />

Advisory Panel, Department of the Environment, Water, Heritage and the Arts (DEWHA)<br />

18. Incorporate comments from consultation and review<br />

19. OPH submit Final Draft Heritage Management Plan to DEWHA<br />

20. DEWHA proceed to public comment period<br />

21. Comments from Australian Heritage Council (AHC)<br />

22. OPH, DEWHA & NCA prepare final Heritage Management Plan incorporating public and<br />

Australian Heritage Council comments & make recommendation to the Minister for the<br />

Environment, Heritage and the Arts<br />

Describe management<br />

zone title, attributes,<br />

rationale, statement of<br />

intent & objectives<br />

Considered all<br />

previous relevant<br />

plans and studies<br />

With key elements:<br />

-final management<br />

zones<br />

-risk analysis<br />

-action assessment<br />

process<br />

- policies<br />

- new use plan<br />

OPH, DEWHA & NCA<br />

review comments & make<br />

recommendation to AHC<br />

23. Minister for the Environment, Heritage and the Arts considers comments and makes the plan