SECTION 3. SOUTH BASIN PROJECTS<br />
Gravity segment 177-00180 to 177-00010 starts at manhole 177-00180. From this location, it<br />
continues northerly along Kennesaw Drive, replacing existing gravity pipe, to Missionary<br />
Ridge Court, then northeast along Missionary Ridge Court to manhole 177-00010.<br />
Gravity segment 112-00013 to PS 112 starts southwest of the Antioch Blvd and Antietam<br />
Avenue intersection. The gravity line travels southwest until reaching PS 112, located<br />
northeast of the Confederate Avenue and Chattanooga Drive intersection.<br />
Gravity segment 110-00088 to 110-000001 starts at the intersection of Confederate Avenue<br />
and Tiger Bend Road. The gravity line travels west along Tiger Bend Road until reaching PS<br />
111, located at the intersection of Tiger Bend Road and Green Trails Boulevard.<br />
Gravity segment 170-00022 to 170-00015 begins at manhole 170-00022, which is located on<br />
the north side of Tiger Bend Road west of Jones Creek Road. From there, it continues west<br />
for approximately 1,100 feet to manhole 170-00015.<br />
Gravity segment 170-00015 to 170-00001 begins at manhole 170-00015, which is located near<br />
the south end of Chaucer Street. From there, it continues south for approximately 1,300 feet<br />
and crosses Tiger Bend Road before turning east near Kimbleton Avenue. After turning east,<br />
the gravity main travels approximately 1,550 feet east and south to manhole 170-00001 near<br />
PS 170.<br />
Gravity segment 170-00167 to 170-00001 begins at manhole 170-00167 near the north end of<br />
Board Road. From there, it continues approximately 750 feet north and east to node 170-<br />
00001 near PS 170.<br />
Gravity segment 170-00110 to PS 170 begins at manhole 170-00110 near the intersection of<br />
Vice President and Profit Avenue and continues west to 170-00023A. This gravity main acts<br />
as an overflow line to the existing gravity main. The gravity main from 170-00023A to PS<br />
170 will be replaced.<br />
Gravity segment 148-00037 to 148-00034 begins at manhole 148-00037. The gravity segment<br />
travels west to Parkforest Drive, then south to manhole 148-00034, which feeds into PS 148<br />
near the intersection of Parklawn Avenue and Parkforest Drive.<br />
The forcemain upgrades consist of the following segments.<br />
Forcemain segment PS 153 to SS11 starts outside the property boundary of PS 153. Upon<br />
leaving the pump station, the forcemain travels southwest for approximately 800 feet along<br />
Woodvale Drive to the intersection of Woodvale Drive and Mockingbird Lane where it then<br />
travels 545 feet to the west, where it enters a manifold intersection with an existing 12-inch<br />
forcemain at node SS11.<br />
Forcemain segment PS 101A to SS32 starts outside the property boundary of PS 101A. Upon<br />
leaving the pump station, the forcemain travels southeast until reaching SS32, located at Old<br />
Hammond Highway and O’Neal Lane.<br />
Forcemain segment SS24 to SS36 starts west of South Choctaw Drive, above Florida<br />
Boulevard. The forcemain travels southwest, crossing Florida Blvd near O’Neal Lane<br />
intersection and crossing O’Neal Lane. The forcemain segment ends at SS36 and is located<br />
near the O’Neal Lane and Strain Road intersection.<br />
GNV31031158547.DOCX/103440004 3-94 JANUARY 2011<br />
REV. 5