SECTION 3. SOUTH BASIN PROJECTS<br />

Gravity segment 177-00180 to 177-00010 starts at manhole 177-00180. From this location, it<br />

continues northerly along Kennesaw Drive, replacing existing gravity pipe, to Missionary<br />

Ridge Court, then northeast along Missionary Ridge Court to manhole 177-00010.<br />

Gravity segment 112-00013 to PS 112 starts southwest of the Antioch Blvd and Antietam<br />

Avenue intersection. The gravity line travels southwest until reaching PS 112, located<br />

northeast of the Confederate Avenue and Chattanooga Drive intersection.<br />

Gravity segment 110-00088 to 110-000001 starts at the intersection of Confederate Avenue<br />

and Tiger Bend Road. The gravity line travels west along Tiger Bend Road until reaching PS<br />

111, located at the intersection of Tiger Bend Road and Green Trails Boulevard.<br />

Gravity segment 170-00022 to 170-00015 begins at manhole 170-00022, which is located on<br />

the north side of Tiger Bend Road west of Jones Creek Road. From there, it continues west<br />

for approximately 1,100 feet to manhole 170-00015.<br />

Gravity segment 170-00015 to 170-00001 begins at manhole 170-00015, which is located near<br />

the south end of Chaucer Street. From there, it continues south for approximately 1,300 feet<br />

and crosses Tiger Bend Road before turning east near Kimbleton Avenue. After turning east,<br />

the gravity main travels approximately 1,550 feet east and south to manhole 170-00001 near<br />

PS 170.<br />

Gravity segment 170-00167 to 170-00001 begins at manhole 170-00167 near the north end of<br />

Board Road. From there, it continues approximately 750 feet north and east to node 170-<br />

00001 near PS 170.<br />

Gravity segment 170-00110 to PS 170 begins at manhole 170-00110 near the intersection of<br />

Vice President and Profit Avenue and continues west to 170-00023A. This gravity main acts<br />

as an overflow line to the existing gravity main. The gravity main from 170-00023A to PS<br />

170 will be replaced.<br />

Gravity segment 148-00037 to 148-00034 begins at manhole 148-00037. The gravity segment<br />

travels west to Parkforest Drive, then south to manhole 148-00034, which feeds into PS 148<br />

near the intersection of Parklawn Avenue and Parkforest Drive.<br />

The forcemain upgrades consist of the following segments.<br />

Forcemain segment PS 153 to SS11 starts outside the property boundary of PS 153. Upon<br />

leaving the pump station, the forcemain travels southwest for approximately 800 feet along<br />

Woodvale Drive to the intersection of Woodvale Drive and Mockingbird Lane where it then<br />

travels 545 feet to the west, where it enters a manifold intersection with an existing 12-inch<br />

forcemain at node SS11.<br />

Forcemain segment PS 101A to SS32 starts outside the property boundary of PS 101A. Upon<br />

leaving the pump station, the forcemain travels southeast until reaching SS32, located at Old<br />

Hammond Highway and O’Neal Lane.<br />

Forcemain segment SS24 to SS36 starts west of South Choctaw Drive, above Florida<br />

Boulevard. The forcemain travels southwest, crossing Florida Blvd near O’Neal Lane<br />

intersection and crossing O’Neal Lane. The forcemain segment ends at SS36 and is located<br />

near the O’Neal Lane and Strain Road intersection.<br />

GNV31031158547.DOCX/103440004 3-94 JANUARY 2011<br />

REV. 5