SECTION 4. CENTRAL BASIN PROJECTS<br />

TABLE 4-10<br />

CC-EAST-FM (Central Consolidated FM ) – Pipeline Information<br />

US Node<br />

DS Node<br />

Length<br />

(ft)<br />

Existing<br />

Diameter<br />

(in)<br />

Proposed<br />

Diameter<br />

(in)<br />

Comments<br />

010-04925 PS 10 520 10 18 Gravity sewer<br />

PS 7 PS10DS 1,900 New 8<br />

PS 10DS PS2DS 3,500 New 12 Includes 500 feet of<br />

tunneling under I-10<br />

PS 2 PS2DS 3,400 New 16<br />

PS 2DS PS3DS 1,800 New 24<br />

PS 3 PS3DS 3,500 New 36 Includes 500 feet of<br />

tunneling under I-10<br />

PS 3DS PS5US 1,800 New 42<br />

PS 5US 2N-1 13,000 New 42<br />

Note: The pipe lengths were obtained from the BTRSSO hydraulic model.<br />

Total Construction Bid Amount is $10,600,000.<br />

Scheduled Design Appropriation Year was 2009.<br />

Scheduled Construction Appropriation Year was 2010.<br />

Design is On-Going.<br />

GNV31031158548.DOCX/103440008 4-42 JANUARY 2011<br />