SECTION 4. CENTRAL BASIN PROJECTS<br />

4.2.3 CGN-C-0003 (South Boulevard – St. Joseph Street Sewer Area Upgrades)<br />

Project Description<br />

Purpose of the Project/Background Information<br />

The purpose of this project is to increase the capacity of the gravity sewers upstream PS 59<br />

and PS 60. Nearly 3,000 feet of gravity sewer and the forcemain from PS 10 were deleted<br />

from this project due to hydraulic modeling updates. This October 2009 version of the PDP<br />

also adds construction of gravity segments that were part of CGN-C-0002 (25 th Street - North<br />

Acadian Thruway) to improve constructability and scheduling issues. This section includes<br />

information about those segments.<br />

Location<br />

The locations of the gravity sewers in this project are shown in Figure 4-11. Gravity segment<br />

059-06088 to new MH #C-3 starts at the intersection of St Philip Street and South Blvd. The<br />

gravity segment travels west until reaching new MH #C-3 at the intersection of South<br />

Boulevard and River Road<br />

The gravity segment C-3 to C-1 travels in a southerly direction until reaching new MH#C-1.<br />

Gravity segment 059-06445 to 059-06532 starts at the Camellia Avenue and Tulip Street<br />

intersection. The gravity segment travels west, turning south at 059-06575A. The gravity<br />

segment turns west at 059-06574, continuing until reaching 059-06532.<br />

Gravity segment 059-06532 to 059-06045 starts at the South 15 th Street and South Street<br />

intersection. The gravity segment travels west along South Street, crossing the KCS railroad<br />

tracks and under I-110 ramps and overpass. The line travels north at the intersection of<br />

South Street and Maximillian Street to 059-06613. The line travels north, turning west at 059-<br />

06614. The line continues west until reaching 059-06045 located northwest of the St Joseph<br />

Street and South Blvd intersection.<br />

Gravity segment 059-06140 to 059-06236 starts near the North Blvd and N 6th Street<br />

intersection. The gravity segment travels south until reaching 059-06139. The line travels<br />

east until reaching 059-06229. The gravity segment travels south until reaching 059-06230.<br />

The line travels east until reaching 059-06236, located near the America Street and St Joseph<br />

Street intersection.<br />

Gravity segment 059-6236 to 059-06128 starts at the America Street and St. Joseph Street<br />

intersection. The gravity segment travels south until reaching 059-06128, located at the<br />

Government Street and St. Joseph Street intersection.<br />

Gravity segment 059-06128 to 059-06045 starts at the Government Street and St. Joseph<br />

Street intersection. The gravity segment travels south until reaching 059-06045, located near<br />

the South Boulevard and St. Joseph Street intersection.<br />

Gravity segment 059-05878 to 059-05868 starts south of North St and River Road<br />

intersection. The gravity segment travels south until reaching 059-05868, located near the<br />

River Road and North Boulevard intersection.<br />

Gravity segment 059-06287 to 059-06128 starts northwest of the Government Street and 11th<br />

Street intersection. The gravity segment travels west, running parallel to Government Street,<br />

until reaching 059-06128 near Government and St. Joseph Street.<br />

GNV31031158548.DOCX/103440008 4-21 JANUARY 2011<br />

REV. 5