27.08.2015 Views

Program Delivery Plan

Program Delivery Plan - Baton Rouge Department of Public Works ...

Program Delivery Plan - Baton Rouge Department of Public Works ...

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

SECTION 6. EMERGENCY GENERATORS<br />

6.3 Wastewater Treatment <strong>Plan</strong>ts<br />

For the North and South/Central WWTPs, the generation capacity needed was estimated<br />

based on the future estimated total flows and current loads seen at each of the plants.<br />

Natural gas generators were selected due to operator preference for natural gas. Cost<br />

estimates were developed for both the stand alone generators, and for the installed<br />

generator systems including automatic transfer switches, equipment pads, enclosures, and<br />

other site specific equipment necessary to integrate the generators into the facility’s<br />

electrical system<br />

The North WWTP estimated generator installed cost is $5.3 M (including estimated sales tax<br />

waiver) for 7.5 MW of generation capacity. This cost for standby power at the North WWTP<br />

is also listed in Section 5.5 North Master <strong>Plan</strong> Improvements Table 5-25 – Summary of<br />

Estimated Construction Costs for the North WWTP.<br />

The South/Central WWTP estimated installed cost is $9.3 M, for 12.5 MW of generation<br />

capacity. This cost is already included in the estimated construction cost for the Phase 2<br />

expansion project (STP-C-0002, South WWTP Phase 2 – Master <strong>Plan</strong> Portion).<br />

6.4 Generator Project <strong>Delivery</strong> <strong>Plan</strong><br />

In order to install generators in a timely manner at all pump stations and the North and<br />

South/Central WWTPs, a project delivery plan was developed. The first step in developing<br />

the project delivery plan was to prioritize the pump stations that were to get generators<br />

using the following criteria:<br />

1) Pump stations to be replaced as a part of PDP<br />

2) Existing pump stations (not impacted by this PDP) that overflowed during Hurricane<br />

Gustav<br />

3) Existing pump stations (not impacted by this PDP) that were on DPW staff’s list of<br />

critical pump stations<br />

4) Existing pump stations (not impacted by this PDP) that were not on any of the previous<br />

lists (with larger pump stations receiving higher priority than smaller pump stations)<br />

The WWTPs were prioritized based on the PDP and Draft Master <strong>Plan</strong> projects. As<br />

mentioned above, the South/Central WWTP generators will be installed as part of the South<br />

WWTP – Phase 2 project, with the generators funded as part of the overall project. The<br />

North WWTP generators will be installed as part of the North WWTP Master <strong>Plan</strong> project.<br />

The existing Central WWTP will not receive emergency generators, since current plans call<br />

for it to be decommissioned.<br />

The schedule of the project delivery is based on this prioritization as well as available<br />

budget. The available budget for generators is estimated to be $10 million in 2009, $10<br />

million in 2010, and $13 million in 2011. Therefore, for each of these three years, the first<br />

priority was the budget for generators at the PDP pump stations. After that, the second,<br />

third, and fourth priorities were considered in the order noted above. Table 6-3 shows the<br />

cost summary- for generator installation.<br />

GNV31031158554.DOCX/103470007 6-3 JANUARY 2011<br />

REV. 5

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!