SECTION 4. CENTRAL BASIN PROJECTS<br />

TABLE 4-1<br />

Estimated Construction Costs for Central Gravity System Comprehensive Rehabilitation Projects<br />

Project Description<br />

Construction<br />

Cost<br />

Scheduled<br />

Design<br />

Appropriation<br />

Year<br />

Scheduled<br />

Construction<br />

Appropriation<br />

Year<br />

Status<br />

CGS-R-0001-Foster<br />

Drive-Government<br />

Street Phase A and B<br />

CGS-R-0002-Highland<br />

Road-Washington<br />

Street<br />

CGS-R-0003-Stanford<br />

Avenue-Morning Glory<br />

Road<br />

CGS-R-0004-Acadian<br />

Thruway-Claycut Road<br />

CGS-R-0005-Acadian<br />

Thruway-Perkins Road<br />

CGN-R-0001a-Scenic<br />

Highway-Spanish Town<br />

Road Phase I<br />

CGN-R-0001b-Scenic<br />

Highway-Spanish Town<br />

Road Phase II<br />

CGN-R-0002- East<br />

Boulevard-Government<br />

Street<br />

$7,683,000 2009* 2009* Construction<br />

On-Going<br />

$8,000,000 2010* 2011 Not Started<br />

$6,900,000 2010* 2010* Design On-<br />

Going<br />

$7,500,000 2010* 2011 Design On-<br />

Going<br />

$3,900,000 2010* 2010* Design On-<br />

Going<br />

$8,600,000 2011 2012 Not Started<br />

$8,600,000 2011 2012 Not Started<br />

$9,600,000 2012 2013 Not Started<br />

*Appropriations already made for these projects (design and/or construction, as marked)<br />

GNV31031158548.DOCX/103440008 4-8 JANUARY 2011<br />