SECTION 3. SOUTH BASIN PROJECTS<br />

Gravity segment 031-00112 to PS 31 starts southeast of the Fairhaven Drive and Woodcliff<br />

Drive intersection. The gravity line travels west until reaching 031-00102, south until<br />

reaching 031-00102A, and then southwest until reaching PS 31. PS 31 is located southeast of<br />

the Westbrook Drive and Goodwood Blvd intersection.<br />

Gravity segment 031-00270 to 031-00112 starts northeast of the East Robinhood Drive and<br />

Woodcliff Drive intersection. The gravity segment travels south until reaching 031-00112,<br />

located southeast of the Fairhaven Drive and Woodcliff Drive intersection.<br />

Gravity segment 031-00299 to 031-00289 starts southeast of the Arlingford Avenue and<br />

Shelby Drive intersection The gravity line travels south until reaching 031-00289, located<br />

northeast of the Archery Drive and Woodcliff Drive intersection.<br />

Gravity segment 031-00330 to 031-00299 starts east of the Norma Court and Shelby Drive<br />

intersection. The gravity line travels south until reaching 031-00299, located southeast of the<br />

Arlingford Avenue and Shelby Drive intersection.<br />

Gravity segment 031-00330A to 031-00330 starts southeast of the Shelby Drive and Florida<br />

Blvd intersection. The gravity line travels south until reaching 031-00330, located east of the<br />

Norma Court and Shelby Drive intersection.<br />

Forcemain segment PS21FM to 031-00330A starts near Florida Boulevard. The forcemain<br />

segment travels south until reaching 031-00330A, located southeast of the Shelby Drive and<br />

Florida Blvd intersection.<br />

Scope<br />

The scope of this project is shown in Table 3-2. This project includes the construction of<br />

approximately 8,400 feet of 15-inch, 21-inch, 24-inch, and 36-inch gravity sewer upstream of<br />

PS 50, approximately 950 feet of 12-inch and 15-inch gravity sewer upstream of PS 13,<br />

approximately 2,100 feet of 18-inch gravity sewer upstream of PS 21, approximately 2,000<br />

feet of 10-inch gravity sewer upstream of PS 101, and approximately 13,800 feet of 10-inch,<br />

12-inch, 15-inch, 18-inch, 21-inch, 24-inch, and 36-inch gravity sewer and forcemain<br />

upstream of PS 31.<br />

TABLE 3-2<br />

SGU-C-0003 (Sherwood Forest Blvd-Goodwood Blvd Pipeline Improvements) – Pipeline Information<br />

US Node<br />

DS Node<br />

Length<br />

(ft)<br />

Existing<br />

Diameter<br />

(in)<br />

Proposed<br />

Diameter<br />

(in)<br />

050-00619 050-00682 1,000 15 24<br />

050-00480 050-00924 2,000 8 and 12 15<br />

050-00400A 050-00837 2,800 18 36<br />

050-00392 050-00280 2,400 12 21<br />

050-00280 050-00272 1,200 15 or 18 24<br />

013-00002 013-00001 150 8 12<br />

Comments<br />

013-00049 PS13 800 8 and 10 15 PS Replacement under SGC-C-0001<br />

(Florida Blvd PS Improvements)<br />

021-00009 PS21 2,100 12 and 15 18 Crosses Florida Blvd; PS will be<br />

upgraded in SGC-C-0001 (Florida<br />

Blvd PS Improvements)<br />

GNV31031158547.DOCX/103440004 3-25 JANUARY 2011<br />