SECTION 3. SOUTH BASIN PROJECTS<br />

3.2.10 SGC-C-PS58FM-A (Staring Lane FM - Phase I – Burbank Drive to Highland<br />

Road)<br />

Project Description<br />

Purpose of the Project / Project Background<br />

The SGC-C-PS58FM-A (Staring Lane FM-Phase I – Burbank Drive to Highland Road) project<br />

includes the construction of a portion of the new forcemain from the PS 58 overflow pump<br />

station to the South WWTP. The purpose of this project is to relieve SSOs at PS 58 as well as<br />

in the respective upstream basins. The construction of the direct forcemain between PS 58<br />

and the South WWTP alleviates the wet weather flows into existing downstream gravity<br />

pipe, and allows the capacity needed for future flows in the Staring Lane area.<br />

This portion of the new forcemain is being constructed as part of the Green Light <strong>Program</strong><br />

project for the Staring Lane Extension.<br />

Location<br />

This portion of the new forcemain runs along Staring Lane Extension from Burbank Drive to<br />

Highland Road (to the South WWTP), connecting into Staring Lane forcemain.<br />

Scope<br />

The scope of this project is shown in Table 3-7 and in Figure 3-18.<br />

TABLE 3-7<br />

SGC-C-PS58FM-A (Staring Lane FM - Phase I - Burbank Drive to Highland Road) – Pipeline Information<br />

US Node<br />

DS Node<br />

Length<br />

(ft)<br />

Existing<br />

Diameter<br />

(in)<br />

Proposed<br />

Diameter<br />

(in)<br />

Comments<br />

Highland Road Burbank Road 2,960 New 64 To be constructed<br />

under Green Light<br />

<strong>Program</strong><br />

Note: The pipe lengths were obtained from the BTRSSO hydraulic model.<br />

Total Construction Bid Amount is$4,616,000.<br />

Scheduled Design Appropriation Year was 2008.<br />

Scheduled Construction Appropriation Year was 2009.<br />

Construction Functionally Complete 2 nd Quarter 2010.<br />

GNV31031158547.DOCX/103440004 3-42 JANUARY 2011<br />

REV. 5