31.01.2023 Views

Formwork for Concrete Structures by R.L.Peurifoy and G.D- By EasyEngineering.net

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Downloaded From : www.EasyEngineering.net

Shores and Scaffolding 171

FIGURE 6-5 Spacing of shores for concrete beam (refer to section A−A in Figure 6-4).

ww.EasyEngineering.n

stem will be 18 in. deep and 15 in. wide. Thus, the total depth of the

beam is 23 in., 18-in. stem, plus the 5-in. slab. The concrete beam is 18 ft

0 in. long, which is the clear span between columns (see Figure 6-5).

The clear height from the lower floor to the bottom of the slab will be

10 ft 6 in.

In addition to the weight of the concrete, assume a temporary

construction live load of 50 lb per sq ft. Because the shoring for the

slab will be placed 2.5 ft, or 30 in., from the centerline of the shoring

for the beam, the load on the beam shoring must sustain the live load

acting over this distance along the beam form (Figure 6-5).

Consider the 23-in.-deep by 15-in.-wide beam and that portion of

the 5-in. slab adjacent to the shores that support the slab. The weight,

including the live load that will be applied to the beam shores can be

calculated:

Beam weight = [23 in. × 15 in.]/144 × (150 lb per cu ft)

= 360 lb per lin ft

Slab weight = 5 in. × [30 in. − 15 in.]/144 × (150 lb per cu ft)

= 78 lb per lin ft

Assume dead load of formwork = 8 lb sq ft × 2.5 ft = 20 lb per lin ft

Live load = 50 lb per sq ft × 2.5 f = 125 lb per lin ft

Total load = 583 lb per lin ft

Total load from beam = 583 lb per lin ft × 18 ft

= 10,494 lb

Downloaded From : www.EasyEngineering.net

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!