Forms for Walls 263

plywood is erected and nailed to the 2 × 4 plates and temporarily

held in position by the Jahn ply holder. The vertical joints should be

tight. Figure 9-28 shows the initial assembly of the forming system.

Figure 9-29 illustrates the proper installation of the Jahn bracket.

After one face of plywood is installed, two workers can easily install

the snap ties: one installs the ties and the other puts on the Jahn “A”

bracket. Working from top to bottom, wales are installed in the bracket

and securely tightened. Wale joints should occur at the bracket, or a scab

should be installed at the wale joint with Jahn “C” brackets. A check

should be made to ensure that plywood panels are plumb and aligned.

Erection of the inside wall panel, or second wall panel, is the same

as for the outside panel, except that these plywood panels are placed

over the snap tie ends. As illustrated in Figure 9-30, this can best be

ww.EasyEngineering.n

FIGURE 9-28

Corporation)

Initial assembly of Jahn forming system. (Source: Dayton Superior

Downloaded From : www.EasyEngineering.net