31.01.2023 Views

Formwork for Concrete Structures by R.L.Peurifoy and G.D- By EasyEngineering.net

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

16 Chapter Two

Downloaded From : www.EasyEngineering.net

been properly tested with an appropriate American Society for

Testing and Materials (ASTM) standard test method designed to

indicate the compression strength of the concrete, and the test

results indicate that the concrete has gained sufficient strength to

support its weight and superimposed loads.

In general, forms for vertical members, such as columns and

piers, may be removed earlier than horizontal forms, such as beams

and slabs. ACI Committee 347 suggests the following minimum

times forms and supports should remain in place under ordinary

conditions. Forms for columns, walls, and the sides of beams often

may be removed in 12 hours. Removal of forms for joists, beams,

or girder soffits depends on the clear spans between structural

supports. For example, spans under 10 ft usually require 4 to 7 days,

spans of 10 to 20 ft require 7 to 14 days, and spans over 20 ft generally

require 14 to 21 days. Removing forms for one-way floor slabs

also will depend on clear spans between structural supports. Spans

under 10 ft usually require 3 to 4 days, spans 10 to 20 ft usually

require 4 to 7 days, and spans over 20 ft require 7 to 10 days.

ww.EasyEngineering.n

Building Construction and Economy

Careful planning in scheduling the construction operations for a

building and in providing the forms can assure the maximum economy

in formwork and also the highest efficiency by labor, both of

which will reduce the cost of formwork.

Consider the six-story building in Figure 2-1, to be constructed

with concrete columns, girders, beams, and slabs. The floor area is

large enough to justify dividing the floor into two equal or approximately

equal areas for forms and concreting. A construction joint

through the building is specified or will be permitted. If the structure

is symmetrical about the construction joint, the builder will

be fortunate. If the building is not symmetrical about the construction

joint, some modifications will have to be made in the form

procedures presented hereafter.

Each floor will be divided into equal units for construction purposes.

Thus, there will be 12 units in the building. One unit will be

completely constructed each week, weather permitting, which will

include making and erecting the forms; placing the reinforcing steel,

electrical conduit, plumbing items, etc., and pouring the concrete.

The carpenters should complete the formwork for unit 1 by the end

of the third day, after which time some of them will begin the formwork

for unit 2 while others install braces on the shores and other

braces, if they are required, and check; if necessary, the carpenters

will adjust the elevations of girder, beam, and deck forms. One or two

carpenters should remain on unit 1 while the concrete is being placed.

This will consume one week.

Downloaded From : www.EasyEngineering.net

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!