31.01.2023 Views

Formwork for Concrete Structures by R.L.Peurifoy and G.D- By EasyEngineering.net

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Downloaded From : www.EasyEngineering.net

Failures of Formwork 193

on the decking or shoring system, all form members should be connected

together in a manner that will prevent the members from separating

or moving with respect to each other.

Design of Formwork to Withstand Dynamic Forces

The analyses presented in the previous sections of this chapter show

that formwork may be subjected to dynamic forces in addition to

those resulting from static loads. The magnitudes of dynamic forces

on formwork will depend on the methods of placing the concrete.

When these types of forces are anticipated, the strength and rigidity

of the formwork should be increased adequately by additional bracing,

increased strength of the form material, and stronger connections

ww.EasyEngineering.n

between adjoining members.

Examples of Failure of Formwork and Falsework

The following examples briefly describe several failures of formwork

and falsework during the erection of concrete bridges. This information

is presented to emphasize the need to exercise care in designing,

erecting, using, and removing formwork or falsework for concrete

structures.

Canada Larga Road Bridge: During the construction of this 88-ftlong

structure, a falsework frame collapsed as it was being adjusted

to grade, causing several injuries and a substantial delay in the completion

of the project (see Figure 7-2).

Oceanside Bridge: The span for this bridge, a 127-ft-long box girder,

had been poured, and the forms had been removed with only the

FIGURE 7-2 This falsework collapsed while being adjusted to grade.

Downloaded From : www.EasyEngineering.net

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!